Richmond, VA Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Elevation standard
1 ft above base flood elevation, nonresidential
Certification
Registered engineer or architect required
Historic structures
May floodproof instead of elevate
Manufactured homes
1 ft above BFE, 3 ft above grade
Enclosed lower areas
Parking, access, or storage only
Enforcing agency
Director, Dept. of Public Utilities
Appeal window
30 days to Richmond Circuit Court

Summary

New construction and substantial improvements to commercial, industrial, or other nonresidential buildings inside a Richmond floodplain district must have their lowest floor, including any basement, elevated to no lower than one foot above the base flood elevation, certified by a registered engineer or architect under City Code § 14-88. Historic structures may floodproof instead of elevate, and enclosed areas below that floor may only be used for parking, access, or storage.

All substantial improvements to existing structures or new construction within any floodplain district shall conform to the applicable sections of the Virginia Uniform Statewide Building Code. New construction or substantial improvement of any existing commercial, industrial, or nonresidential building (or manufactured home) shall have the lowest floor, including basement, elevated to no lower than one foot above the base flood elevation. A registered professional engineer or architect shall certify that the standards of this subsection are satisfied. For historic structures as defined in this article, where elevation is not preferable, floodproofing may be allowed instead of elevation one foot above the base flood elevation. ... Fully enclosed areas below the lowest floor shall be used solely for parking of vehicles, building access or storage and shall have permanent openings designed to allow the entry and exit of floodwaters in accordance with specifications as set forth at 44 CFR 60.3(c)(5).

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Recodification).

Full Breakdown

Section 14-88 of Richmond's floodplain management article sets the freeboard standard the City layers on top of the Virginia Uniform Statewide Building Code. For new construction or a substantial improvement (any repair, reconstruction, or addition whose cost equals or exceeds 50 percent of the structure's pre-improvement market value) to an existing commercial, industrial, or other nonresidential building, or to a manufactured home, the lowest floor, including a basement, must sit at least one foot above the base flood elevation shown on the City's flood insurance rate map.

A registered professional engineer or architect must certify compliance and submit that certification to the Director of Public Utilities, who administers the floodplain article. Historic structures, as defined in § 14-21, may floodproof to that same one-foot standard instead of physically raising the building, again with an engineer's or architect's certification. 3(c)(5), so the space cannot be converted into finished living area. The related freeboard rule for manufactured homes and recreational vehicles in § 14-87 requires the lowest floor to sit at least one foot above base flood elevation and at least three feet above grade, with the chassis anchored to resist flotation and lateral movement.

Every floodplain building permit application must state the 100-year flood elevation, the elevation of the lowest floor, and, for nonresidential buildings, the floodproofed elevation, per § 14-120. Development in the floodway district faces additional restrictions: no fill, new construction, or substantial improvement is allowed there unless a professional engineer certifies it will cause no increase in flood levels during the base flood, per § 14-84(c).

Violations & Fines

Building below the required elevation without a certified engineer's or architect's sign-off is a floodplain article violation under § 14-124, a Class 1 misdemeanor punishable under § 1-16, and the City can also sue in equity to compel a structure's abatement, alteration, or removal. Flood insurance can be withheld from any structure built in violation of the elevation requirements, and the Director's decisions may be appealed to the Richmond Circuit Court within 30 days under § 14-123.

Frequently Asked Questions

How high above flood level must a Richmond building sit?
For new construction or a substantial improvement to a commercial, industrial, or other nonresidential building in a floodplain district, City Code § 14-88 requires the lowest floor, including any basement, to be elevated to at least one foot above the base flood elevation. A registered professional engineer or architect must certify the elevation and file that certification with the Director of Public Utilities before the City signs off.
Can I finish out a basement below the flood elevation line in Richmond?
No. Any fully enclosed area below the required lowest floor may only serve as parking, building access, or storage, and it must have permanent openings sized to let floodwater flow in and out under federal flood regulations. Converting that space into finished living area violates § 14-88 and can jeopardize the structure's flood insurance eligibility.
Does a historic building in Richmond still need to be raised?
Not necessarily. Where elevation is not preferable for a historic structure as defined in § 14-21, the owner can floodproof the building to the same one-foot-above-base-flood-elevation standard instead of physically raising it, provided a registered engineer or architect certifies the design and construction methods on the floodproofing certificate filed with the Director.

Sources & Official References

Other rules in Richmond

All Richmond rules

Compare Richmond to another location·View the Virginia environmental rules overview

Get notified when Flood Elevation Requirements in Richmond, VA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.