Stratford, CT Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Residential lowest floor
- Elevated to at least the base flood elevation
- Nonresidential option
- Elevate to BFE or floodproof to the base flood level
- Enclosure vent openings
- Two openings, one square inch per square foot enclosed
- Opening height
- Bottom of openings no higher than one foot above grade
- Coastal VE zone
- Lowest horizontal supporting member at least one foot above BFE
- Penalty
- Not more than $250 per day per violation
Summary
In the Town of Stratford, Connecticut, new and substantially improved residential buildings in a flood hazard area must have the lowest floor, including the basement, elevated to at least the base flood elevation. Nonresidential buildings can elevate to the same level or be floodproofed. Coastal VE zones require the lowest horizontal member one foot above the BFE.
In all areas of special flood hazard where base flood elevation data has been provided as set forth in § 102-7 (Basis for establishing areas of special flood hazard) or in § 102-14B (Use of other base flood data), the following standards are required: A. Residential construction. New construction and substantial improvements of any residential structure shall have the lowest floor, including basement, elevated to at least the base flood elevation. ... B. Nonresidential construction. New construction and substantial improvement of any commercial, industrial or other nonresidential structure shall have either the lowest floor, including basement, elevated to at least the base flood elevation or, together with attendant utility and sanitary facilities, shall: ... (1) Be floodproofed to the base flood level so the structure is watertight with walls substantially impermeable to the passage of water.
Full Breakdown
The elevation rule sits in Chapter 102, Flood Damage Prevention, of the Stratford Code. It applies in areas of special flood hazard where base flood elevation data has been provided under § 102-7 or § 102-14B. Under § 102-18(A), new construction and substantial improvements of any residential structure must have the lowest floor, including basement, elevated to at least the base flood elevation. The words printed in § 102-18 set the floor at the BFE itself and print no additional margin for Zones A and AE.
Nonresidential buildings get a choice under § 102-18(B). A commercial, industrial or other nonresidential structure can elevate its lowest floor to at least the BFE, or it can be floodproofed to the base flood level so the structure is watertight with walls substantially impermeable to water. Floodproofing also requires structural components that resist hydrostatic and hydrodynamic loads and buoyancy, with certification by a registered professional engineer or architect.
Fully enclosed areas below the lowest floor that serve only parking, building access or storage must have a minimum of two openings with a total area of not less than one square inch for every square foot of enclosed area, and the bottom of every opening can be no higher than one foot above grade (§ 102-18(C)).
Coastal VE zones are tougher. Section 102-19(B)(1) requires the bottom of the lowest horizontal supporting member to sit at least one foot above the BFE, with utility equipment elevated to or above the BFE. Section 102-22 requires above-ground tanks to be elevated above the BFE on a concrete pad, or anchored with the top of the fill pipe extended above the BFE. Under § 102-24, a structure in two or more flood zones must meet the most restrictive zone's standards and be built to the highest BFE.
Section 102-7 notes that BFEs printed on a FIRM are only approximate and should be verified against the BFEs published in the Flood Insurance Study for a specific location. A variance holder under § 102-15 receives written notice that the lowest floor will sit below the BFE and that flood insurance will cost commensurate with the increased risk.
Violations & Fines
Section 102-16 makes a violation of Chapter 102 a misdemeanor, punishable on conviction by a fine of not more than $250 per day per violation, plus all costs and reasonable legal fees. The Building Inspector is the local administrator who grants or denies the development permit (§ 102-13), and § 102-8 bars any structure from being constructed, located, extended, converted or altered without full compliance with the chapter.
Frequently Asked Questions
How high must my floor be in a Stratford flood zone?
Can a Stratford commercial building floodproof instead of elevating?
What are the flood vent rules for an enclosed area under the house?
Where do I find the base flood elevation for my lot in Stratford?
Sources & Official References
Other rules in Stratford
Compare Stratford to another location·View the Connecticut environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.