Governing section
Municipal Code § 6-9.501(c)
Freeboard requirement
1 ft. above base flood elevation
AO zone alternative
3 ft. above grade if no depth shown
Certification required at
First form inspection
Manufactured home pier height
36 in. minimum above grade

Summary

New residential construction and substantial improvements in a Yuba City special flood hazard area must have the lowest floor, including any basement, elevated at least one foot above the base flood elevation, certified by a licensed engineer or surveyor at first form inspection.

(c)Elevation and floodproofing.(1)Residential new construction or substantial improvement shall have the lowest floor, including basement:(ii) ... In an A zone where no base flood elevations have been determined, elevated at least one ft. above the base flood elevation, as determined by the floodplain administrator through acceptable methods as listed in FEMA book "Managing Floodplain Development in Approximate Zone A Areas; A Guide for Developing Base (100 year) Flood Elevations"; and(iii)In all other zones, elevated at least one ft. above the base flood elevation. At first form inspection, the elevation of the lowest floor including basement shall be certified by a registered professional engineer or surveyor. Such certification or verification shall be provided to the Floodplain Administrator.

Full Breakdown

401. In an A zone where FEMA has not determined base flood elevations, the floor must sit at least one foot above the base flood elevation as the Floodplain Administrator determines using FEMA's approximate Zone A methodology; in every other zone, the same one-foot freeboard above base flood elevation applies. In an AO zone, the standard instead ties to the depth number printed on the Flood Insurance Rate Map, requiring elevation above the highest adjacent grade that exceeds that depth number by at least one foot, or at least three feet above the highest adjacent grade if no depth number is shown.

A registered professional engineer or surveyor must certify the lowest floor elevation at the first form inspection, with that certification provided to the Floodplain Administrator, the Public Works Director. Nonresidential buildings may instead be floodproofed watertight below that same elevation if a registered engineer or architect certifies the structure meets the floodproofing standard. 504: homes placed or substantially improved on sites in zones A1-30, AH, and AE on Sutter County's Flood Insurance Rate Map, whether outside a park, in a new or expanded park, or replacing a home with substantial flood damage, must sit on a permanent foundation with the lowest floor at least one foot above base flood elevation and be securely anchored against flotation, collapse, and lateral movement. In an existing manufactured home park, the alternative is a chassis on reinforced piers at least 36 inches above grade, also securely anchored.

Violations & Fines

Constructing or substantially improving a residential structure without meeting the one-foot freeboard elevation in Section 6-9.501(c), or without the engineer or surveyor certification at first form inspection, is a violation of the Flood Damage Prevention chapter and can be enforced under Section 6-9.403(g)'s remedial-action authority tied to the Section 6-9.303 compliance requirement.

Frequently Asked Questions

How high above base flood elevation must a new Yuba City home be built?
Section 6-9.501(c) requires the lowest floor, including any basement, to sit at least one foot above the base flood elevation in most zones, or, in an AO zone with no depth number listed, at least three feet above the highest adjacent grade.
Who certifies the flood elevation of a new building in Yuba City?
A registered professional engineer or surveyor must certify the lowest floor elevation at the first form inspection under Section 6-9.501(c)(1), and that certification must be provided to the Floodplain Administrator, the Public Works Director.
What are the flood elevation rules for manufactured homes in Yuba City?
Section 6-9.504 requires manufactured homes placed in zones A1-30, AH, or AE to sit on a permanent foundation with the lowest floor at least one foot above base flood elevation, or on reinforced piers at least 36 inches above grade in an existing park, both securely anchored.

Sources & Official References

Other rules in Yuba City

All Yuba City rules

California rules heatmap·Compare Yuba City to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Yuba City, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.