FEMA flood zone rules in Aliso Viejo, CA, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- Mapped basis
- FEMA flood insurance study for Orange County, dated February 18, 2004
- Permit
- Flood hazard development permit before any construction or development
- Administrator
- Director of public works
- Substantial improvement trigger
- Cost equal to or over 50 percent of market value
- Appeals
- City council hears appeals of administrator decisions
- Penalty
- Misdemeanor: up to $1,000 fine, up to six months
Summary
In the City of Aliso Viejo, California, Chapter 7.50 of the Municipal Code applies to every area of special flood hazard inside city limits, as mapped in the FEMA flood insurance study for Orange County dated February 18, 2004. Nothing can be built, filled or otherwise developed in those areas without a flood hazard development permit, and a violation is a misdemeanor.
A. Lands to Which This Chapter Applies. The provisions of this chapter shall apply to all areas of special flood hazards within the city limits of the city of Aliso Viejo. B. Basis for Establishing the Areas of Special Flood Hazard. The areas of special flood hazard identified by the Federal Emergency Management Agency (FEMA) in the flood insurance study (FIS) for Orange County, CA and Incorporated Areas, dated February 18, 2004, with accompanying flood insurance rate maps (FIRMs), and all subsequent amendments and/or revisions, are hereby adopted by reference and declared to be a part of this chapter. ... C. Compliance. No structure or land shall hereafter be constructed, located, extended, converted, or altered without full compliance with the terms of this chapter and other applicable regulations. Violation of the requirements (including violations of conditions and safeguards established in connection with conditions) shall constitute a misdemeanor.
Full Breakdown
Section 7.50.040 sets the reach of the rule. It covers all areas of special flood hazard within the city limits of Aliso Viejo, and it adopts by reference the FEMA flood insurance study for Orange County, CA and Incorporated Areas dated February 18, 2004, with its flood insurance rate maps and all later amendments. The study and maps sit on file at Aliso Viejo City Hall in the department of public works. The mapped area is the minimum: the floodplain administrator can recommend additional studies to the city council to extend it. A special flood hazard area is defined as land with a one percent or greater chance of flooding in any given year, shown on the map as Zone A, AO, A1-A30, AE, A99 or AH.
Inside those zones, section 7.50.050 requires a flood hazard development permit before any construction or other development begins. The application goes on forms from the floodplain administrator, who is the director of public works, and must include a site plan with spot ground elevations at building corners and at 20-foot or smaller intervals along the foundation footprint (or one-foot contours across the building site), foundation details, and a description of any watercourse that would be altered or relocated. Foundations placed on fill must show the location and height of fill and compaction to 95 percent using the standard proctor test method.
The overlay is a stricter layer on top of other rules. Where this chapter and any other ordinance, easement, covenant or deed restriction conflict, whichever imposes the more stringent restriction prevails. In the regulatory floodway, section 7.50.060(F) prohibits fill, new construction, substantial improvement and other new development unless a registered professional engineer or architect certifies that the encroachment will not raise the base flood elevation. A substantial improvement or substantial damage is any project or loss costing 50 percent or more of the structure's market value. Disputes over a mapped boundary or an administrator decision go to the city council on appeal, and a variance under section 7.50.070 is reserved for land with physical characteristics so unusual that compliance would create an exceptional hardship.
Violations & Fines
Section 7.50.040(C) makes any violation of the chapter, including its conditions and safeguards, a misdemeanor. Under section 1.06.010(B) a conviction carries a fine of not more than $1,000, imprisonment of not more than six months, or both, plus an order to correct the violation. Each day is a separate offense under section 1.06.020. Development lacking the required elevation certificate or other proof of compliance is presumed to be in violation until the documents are supplied.
Frequently Asked Questions
Does Aliso Viejo require a permit to build in a flood zone?
Which flood maps does the City of Aliso Viejo use?
What happens if someone builds in the floodway in Aliso Viejo?
Who decides disputes about the flood zone boundary?
Sources & Official References
Other rules in Aliso Viejo
California rules heatmap·Compare Aliso Viejo to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Zones in Nearby Cities
How other cities in Orange County handle flood zones.