Key Facts

Residential lowest floor, most zones
At least two feet above base flood elevation
AO zone without a depth number
At least four feet above highest adjacent grade
Certification
Registered professional engineer or surveyor, verified by building inspector
Flood vents
Two openings, one square inch per square foot of enclosed area
Vent height
Bottom of each opening no higher than one foot above grade
Applies to
New construction and substantial improvement

Summary

In the City of Aliso Viejo, California, new residential construction and substantial improvements in a special flood hazard area must have the lowest floor, including any basement, at least two feet above the base flood elevation in most zones. Section 7.50.060 also sets AO zone depths, engineer or surveyor certification and flood vent openings.

a. New construction and substantial improvement of any residential structure shall have the lowest floor, including basement: ... i. In an AO zone, elevated two feet above the highest adjacent grade to a height equal to or exceeding the depth number specified in feet on the FIRM, or elevated at least four feet above the highest adjacent grade if no depth number is specified. ... ii. In an A zone, elevated two feet to or above the base flood elevation, as determined by this community. ... iii. In all other zones, the lowest floor shall be elevated at least two feet above the base flood elevation. ... Upon the completion of the structure, the elevation of the lowest floor including basement shall be certified by a registered professional engineer or surveyor, and verified by the city building inspector to be properly elevated. Such certification and verification shall be provided to the floodplain administrator.

Full Breakdown

Section 7.50.060(A)(3) sets the elevation rule for new construction and substantial improvement of a residential structure in the City of Aliso Viejo. In an AO zone the lowest floor, including basement, is elevated two feet above the highest adjacent grade to a height equal to or exceeding the depth number printed on the flood insurance rate map, or at least four feet above the highest adjacent grade where the map gives no depth number. In an A zone it is elevated two feet to or above the base flood elevation as determined by the city. In all other zones it must be at least two feet above the base flood elevation. The base flood is the flood with a one percent chance of being equaled or exceeded in any given year, also called the 100-year flood.

When the structure is finished, a registered professional engineer or surveyor certifies the lowest floor elevation, the city building inspector verifies it, and both go to the floodplain administrator, who keeps the certificates available for public inspection. Nonresidential buildings can either meet the elevation standard or be floodproofed so the structure is watertight with walls substantially impermeable to water, able to resist hydrostatic and hydrodynamic loads and buoyancy, with a certification from a registered professional engineer or architect.

Enclosed areas below the lowest floor that are used only for parking, building access or storage must equalize flood pressure automatically: either an engineer or architect certifies the design, or the wall has a minimum of two openings with a total net area of not less than one square inch for every square foot of enclosed area, with the bottom of every opening no higher than one foot above grade. Manufactured homes in Zones A1-A30, AH and AE sit on a permanent foundation with the lowest floor at least two feet above the base flood. Electrical, heating, ventilation, plumbing and air conditioning equipment must be designed or located to keep water out during flooding. Subdivision proposals must identify the flood hazard area and the elevation of the base flood, and filled pads need certified lowest floor and pad elevations.

Violations & Fines

Section 7.50.040(C) makes noncompliance with the chapter a misdemeanor, punishable under section 1.06.010(B) by a fine of not more than $1,000, up to six months in jail, or both, plus an order to correct. A structure without the required elevation certificate or other evidence of compliance is presumed to be in violation until the documentation is provided, and each day is a separate offense under section 1.06.020.

Frequently Asked Questions

How high must the lowest floor be in an Aliso Viejo flood zone?
In an A zone it is elevated two feet to or above the base flood elevation, and in all other zones at least two feet above it. In an AO zone it is two feet above the highest adjacent grade, matching the FIRM depth number, or at least four feet if no depth number is given.
Who certifies the elevation in the City of Aliso Viejo?
A registered professional engineer or surveyor certifies the elevation of the lowest floor, including basement, once the structure is complete. The city building inspector verifies that it is properly elevated, and the certification and verification are provided to the floodplain administrator, the director of public works.
Can a commercial building in Aliso Viejo floodproof instead of elevating?
Yes. A nonresidential structure can either meet the elevation standard or be floodproofed so it is watertight with walls substantially impermeable to water. It needs structural components that resist hydrostatic and hydrodynamic loads and buoyancy, and a registered professional engineer or architect must certify the design.
What are the flood opening rules for enclosed areas below the lowest floor?
Enclosed areas used only for parking, access or storage must let floodwater enter and exit automatically. Either an engineer or architect certifies the design, or the wall has a minimum of two openings totaling at least one square inch per square foot of enclosed area, with each bottom edge no higher than one foot above grade.

Sources & Official References

Other rules in Aliso Viejo

All Aliso Viejo rules

California rules heatmap·Compare Aliso Viejo to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Aliso Viejo, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Orange County handle flood elevation requirements.

Anaheim, CA
Some Restrictions
Costa Mesa, CA
Some Restrictions
Fullerton, CA
Some Restrictions
Garden Grove, CA
Significant Restrictions
Huntington Beach, CA
Some Restrictions
Irvine, CA
Some Restrictions
Mission Viejo, CA
Some Restrictions
Newport Beach, CA
Some Restrictions