St. Martin Parish, LA Environmental Rules: Flood Zones (2026)
FEMA flood zone rules in St. Martin Parish, LA, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- Regulatory floodway
- Encroachments prohibited without engineer's no-increase analysis
- Engineer required
- Louisiana licensed engineer prepares hydrologic and hydraulic analyses
- Permit
- Floodplain development permit for special flood hazard area projects
- Levee work
- Permit plus majority vote of the Parish Council
- Variance request deadline
- Written, within ten days of administrator's determination
- Penalty
- Fine up to $100.00 or 30 days, each day a new violation
Summary
Unincorporated St. Martin Parish, Louisiana prohibits fill, new construction, substantial improvements and other development in the adopted regulatory floodway unless a Louisiana licensed engineer shows no increase in flood levels during the base flood discharge. St. Martin Parish Code § 14-70 sets the rule, and development in a special flood hazard area also needs a floodplain development permit.
Located within areas of special flood hazard established in section 14-7 are areas designated as floodways. Since the floodway is an extremely hazardous area due to the velocity of floodwaters which carry debris, potential projectiles and erosion potential, the following provisions shall apply: (1)Encroachments are prohibited, including fill, new construction, substantial improvements and other development within the adopted regulatory floodway unless it has been demonstrated through hydrologic and hydraulic analyses performed in accordance with standard engineering practice acceptable to the applicable regulatory agency and prepared by a Louisiana licensed engineer that the proposed encroachment would not result in any increase in flood levels within the community during the occurrence of the base flood discharge. The data must be reviewed and subsequently approved by the local floodplain administrator and other applicable regulatory agencies prior to the development.
Full Breakdown
Chapter 14 is the parish's flood damage prevention regulation, enacted by Ord. No. 19-12-1282-OR on December 3, 2019 under the authority the Legislature delegated in R.S. 38:84. Sec. 14-70 covers floodways: encroachments including fill, new construction, substantial improvements and other development in the adopted regulatory floodway are prohibited unless hydrologic and hydraulic analyses prepared by a Louisiana licensed engineer show the encroachment would not increase flood levels during the base flood discharge. The local floodplain administrator and other applicable regulatory agencies must review and approve the data before development, and Sec. 14-101(1)a. adds that no final plat approval or certificate of occupancy issues until the required submittal is approved in writing.
Outside the floodway, development in a special flood hazard area needs a floodplain development permit under Sec. 14-45. The application goes to the floodplain administrator on the administrator's forms, with plans in duplicate drawn to scale, the lowest floor elevation in relation to mean sea level and a freeboard elevation form. Building Code Inspection Services, LLC is appointed administrator in Sec. 14-43, and the parish president can appoint another with confirmation by a majority of the parish council. Sec. 14-66(a)(10) bars development of land in a flood hazard, floodplain or floodway area that is incompatible with its proposed use because of poor drainage or flooding, and Sec. 14-101(4)(b) requires a residential development that fills a special flood hazard area to restore the volume to achieve an effective "zero net fill."
Any development that constructs, alters or removes a levee or levee system under Sec. 14-71 needs a permit from the floodplain administrator and a specific majority vote of the St. Martin Parish Council. Variances go to the appeals board, which Sec. 14-2 defines as the St. Martin Parish Council. A written request must be filed within ten days of the administrator's determination at 400 Port Street, St. Martinville, and Sec. 14-46(h) bars any variance in a designated floodway if flood levels would increase during the base flood discharge. A person aggrieved by the board's decision goes to the 16th Judicial District Court in and for St. Martin Parish.
Violations & Fines
Section 14-13 makes a violation of the flood articles a misdemeanor. On conviction the violator is fined not more than $100.00 or imprisoned for not more than 30 days, or both, for each violation, and each day the violation continues is a new violation. The violator also pays all costs and expenses involved in the case, and the parish keeps the power to take other lawful action to prevent or remedy the violation.
Frequently Asked Questions
Can I build or place fill in the regulatory floodway?
What does a floodplain development permit application include?
How do I ask for a variance or appeal a decision?
Do I need approval to change a levee?
Does this apply inside St. Martinville or Breaux Bridge?
Sources & Official References
Other rules in St. Martin Parish
Compare St. Martin Parish to another location·View the Louisiana environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.