Bayonne, NJ Environmental Rules: Stormwater Management (2026)
Key Facts
- Triggering size
- 1+ acre disturbed, or 1/4 acre impervious
- Governing chapter
- Chapter 30, Stormwater Management
- Design requirement
- green infrastructure BMPs, Sec. 30-3
- First offense penalty
- $1,000
- Second offense penalty
- $2,500
- Third+ offense penalty
- $10,000
- Maintenance fix deadline
- 14 days after written notice
Summary
In the City of Bayonne, any major development, generally one disturbing an acre or more of land or creating a quarter acre or more of new impervious surface, must control erosion, protect groundwater recharge, and meet stormwater quality and quantity standards using green infrastructure under Chapter 30. Violations carry escalating fines up to $10,000.
§ 30-1.1. Policy Statement. ... Flood control, groundwater recharge, and pollutant reduction shall be achieved through the use of stormwater management measures, including green infrastructure best management practices (GI BMPs) and nonstructural stormwater management strategies. ... MAJOR DEVELOPMENT a. ... An individual development, as well as multiple developments that individually or collectively result in: 1. The disturbance of one or more acres of land since February 2, 2004; 2. The creation of 1/4 acre or more of regulated impervious surface since February 2, 2004; § 3 ... 0-3. ... GENERAL STANDARDS. ... (b) The minimum standards for groundwater recharge, stormwater quality, and stormwater runoff quantity shall be met by incorporating green infrastructure. ... ... § 30-11. PENALTIES. ... Any person who erects, constructs, alters, repairs, converts, maintains, or uses any building, structure or land in violation of §§ 30-1 through 30-11 of this chapter shall be subject to the following penalties: $1,000 for first offense, $2,500 for second offense, $10,000 for third offense and thereafter.
Full Breakdown
Bayonne's stormwater chapter, adopted under Ordinance No. O-21-17 and last amended June 18, 2025 by Ordinance No. O-25-38, exists to control flooding, protect groundwater recharge and reduce pollution using green infrastructure best management practices and low-impact development, per Section 30-1.1's policy statement. Its numeric trigger is the definition of 'major development' in Section 30-2: an individual project, or multiple related projects, that disturb one or more acres of land since February 2, 2004, or that create one-quarter acre or more of new impervious surface since that date, or a comparable amount of regulated motor vehicle surface since March 2, 2021.
Once a project crosses that line, Section 30-3 requires its stormwater management measures to be designed for erosion control, groundwater recharge, and stormwater runoff quantity and quality treatment, and directs that the groundwater recharge, quality and quantity pieces specifically be met by incorporating green infrastructure rather than older detention-only designs. The chapter reaches both nonresidential major development and the parts of residential major development not already preempted by the state's Residential Site Improvement Standards, and it also binds development undertaken by the City of Bayonne itself.
A design engineer must also prepare a maintenance plan for every project's stormwater measures under Section 30-10, and the responsible party has 14 days after written notice from the municipality to fix a facility that becomes a danger to public health or safety before the City can do the work and bill the cost. Enforcement runs through Section 30-11, which sets an escalating penalty scale for any violation of the chapter.
Violations & Fines
Section 30-11 penalizes anyone who erects, constructs, alters, repairs, converts, maintains or uses any building, structure or land in violation of the stormwater chapter (Sections 30-1 through 30-11): $1,000 for a first offense, $2,500 for a second offense, and $10,000 for a third offense and each one after that.
Frequently Asked Questions
What counts as a 'major development' under Bayonne's stormwater rule?
What design standard must a qualifying project meet?
What is the fine for violating Bayonne's stormwater chapter?
Do residential projects have to follow Chapter 30?
Sources & Official References
Other rules in Bayonne
Compare Bayonne to another location·View the New Jersey environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Stormwater Management in Nearby Cities
How other cities in this county handle stormwater management.