Permit trigger (outside CBPA)
10,000 sq ft or more disturbed
Permit trigger (inside CBPA)
2,500 sq ft or more disturbed
Civil penalty
Up to $32,500.00 per violation per day
Criminal penalty
Up to 12 months jail, $2,500-$32,500 fine
Administering authority
Director of Public Works (VESMP authority)

Summary

Hanover County Code Section 10-7 bars land-disturbing activity until the Virginia Erosion and Stormwater Management Program authority issues a land-disturbance permit, and Section 10-5 sets the size thresholds, generally 10,000 square feet outside Chesapeake Bay Preservation Areas or 2,500 square feet inside them, that trigger the permit and technical review.

These county ordinances apply to unincorporated areas of Hanover County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)The purpose of this article is to (1) ensure the general health, safety, and welfare of the county's residents; (2) protect water quality, stream channels, other natural resources, and the quality and quantity of state waters from the potential harm of unmanaged stormwater and soil erosion, including protection from land-disturbing activity causing unreasonable degradation of properties; and (3) establish procedures whereby erosion and sediment controls and stormwater requirements related to water quality and quantity shall be administered and enforced. ... Except as provided herein, no person may engage in any land-disturbing activity until a land disturbance permit has been issued by the VESMP authority in accordance with the provisions of this article and the Regulations. ... shall be subject to a civil penalty not to exceed thirty-two thousand five hundred dollars ($32,500.00) for each violation within the discretion of the court. Each day of violation of each requirement shall constitute a separate offense.

Full Breakdown

15:27. Section 10-5(a) sets the activity thresholds that pull a project into regulation: land disturbance of 10,000 square feet or more but less than 1 acre outside a Chesapeake Bay Preservation Area triggers soil erosion and water quantity criteria; disturbance of 2,500 square feet or more but less than 1 acre inside a Chesapeake Bay Preservation Area triggers soil erosion plus water quantity and quality criteria; and disturbance of 1 acre or more is regulated regardless of location. Section 10-5(b) exempts minor activities such as home gardening, individual home landscaping, utility line repairs on existing hard-surfaced roads, and bona fide agricultural clearing.

Section 10-7 requires a land-disturbance permit from the VESMP authority before any regulated activity begins, and separately bars a building permit until a licensed engineer or surveyor calculates the effect of the 100-year storm on the proposed building and confirms the lowest finished floor sits at least 1 foot above the 100-year flood elevation; residential building permit applications must include a grading plan showing existing topography, proposed grading, flood elevations and erosion controls, prepared by a licensed professional. Section 10-6(a) gives the VESMP authority 15 days to determine an application complete and 60 days to act on it once complete.

Violations & Fines

Section 10-17(c) subjects anyone who violates the VESMP program, its regulations, this article or a permit condition to a civil penalty of up to $32,500.00 per violation, with each day of continuing violation a separate offense, collectible through the Hanover County District or Circuit Court. Section 10-17(d) makes a willful or negligent violation a misdemeanor punishable by up to 12 months in jail, a fine of $2,500.00 to $32,500.00, or both, and the VESMP authority may also issue a stop-work order under Section 10-17(a)(2).

Frequently Asked Questions

When does a Hanover County project need a stormwater permit?
Once land disturbance reaches 10,000 square feet outside a Chesapeake Bay Preservation Area, or 2,500 square feet inside one, under Section 10-5(a). Any project disturbing 1 acre or more is regulated regardless of location, and Section 10-7 bars starting work until the VESMP authority issues the permit.
What building permit condition applies because of flooding?
Section 10-7(b) bars a building permit for a structure with a proposed lowest finished floor less than 1 foot above the 100-year flood elevation, and Section 10-7(a) requires a licensed engineer or surveyor to calculate the 100-year storm's effect on the proposed building before that permit issues.
What are the penalties for skipping the permit?
Civil penalties reach $32,500.00 per violation per day under Section 10-17(c), and a willful or negligent violation is a misdemeanor carrying up to 12 months in jail and a fine between $2,500.00 and $32,500.00 under Section 10-17(d).

Sources & Official References

Other rules in Hanover County

All Hanover County rules

Compare Hanover County to another location·View the Virginia environmental rules overview

Get notified when Stormwater Management in Hanover County, VA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.