Madison, WI Environmental Rules: Stormwater Management (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Governing section
MGO § 37.09
Plan must be sealed by
Wisconsin-licensed Professional Engineer
Administering authority
City Engineer / Administrative Authority
Required calculation
Pre- and post-construction peak flow rates
Financial guarantee
Security instrument may be required
First violation fine (per site)
$200 forfeiture

Summary

Once a project trips the permit thresholds in Chapter 37, Madison requires an engineer-sealed stormwater management plan under MGO § 37.09 that documents runoff-control measures, pre- and post-construction peak flow calculations, and a named party responsible for long-term maintenance.

37.09 - STORMWATER MANAGEMENT PLAN REQUIREMENTS.(1)Stormwater Management Plan Required.(a)Every applicant for a stormwater management permit shall submit a plan documenting the system(s) and measures proposed to control stormwater runoff from the site. Included in this stormwater management plan shall be a completed standard stormwater management summary template. ... The stormwater management plan shall be completed and sealed by a Professional Engineer currently licensed in the State of Wisconsin. (b)Evidence of Financial Responsibility. The Administrative Authority may require a financial security instrument sufficient to guarantee complete construction of the stormwater management systems proposed in the stormwater management plan.

Source: Madison Stormwater Ordinance Ch. 37View official code

Full Breakdown

Sec. 09, Stormwater Management Plan Requirements, governs the plan itself once Sec. 06(3) has already required a stormwater management permit. Every applicant must submit a plan documenting the systems and measures proposed to control runoff, including a completed standard stormwater management summary template available from the City's Engineering Division, and the plan must be completed and sealed by a Professional Engineer licensed in Wisconsin. The Administrative Authority (the City Engineer's office) may additionally require a financial security instrument guaranteeing the stormwater systems actually get built.

Required plan contents include a narrative description of the project with an implementation schedule, identification of who is responsible for long-term maintenance, a topographic map of the site and contiguous properties showing existing drainage patterns and vegetative cover, a map of drainage areas by watershed, and a full set of peak-flow-rate calculations covering pre-existing conditions, post-construction conditions without detention, and post-construction conditions with detention, using specified runoff curve numbers tied to Hydrologic Soil Groups. The performance standards in Sec. 09(1)-(3) apply differently depending on the trigger: full development, redevelopment, site disturbance/grading of an acre or more, street reconstruction, and parking-lot resurfacing each pull in a different combination of the plan's total-suspended-solids, rate-control, and infiltration requirements.

Violations & Fines

Failing to obtain the stormwater management permit required before undertaking a Sec. 37.06(3) activity carries the same escalating fine as erosion control violations: a $200 forfeiture for a first violation at the site, $500 for a second, and $1,000 for a third or subsequent violation, each treated per site rather than per day. The Administrative Authority can also condition or withhold approval of a plan that fails to meet the performance standards of Sec. 37.09(4).

Frequently Asked Questions

Who has to prepare a stormwater management plan in Madison?
Any applicant triggering a stormwater management permit under MGO § 37.06(3), including qualifying new development, redevelopment, an acre or more of site disturbance, or large parking-lot resurfacing, must submit a plan under Sec. 37.09, sealed by a Wisconsin-licensed Professional Engineer.
What has to be in a Madison stormwater management plan?
A narrative project description, an implementation schedule, the party responsible for long-term maintenance, a topographic map with existing drainage patterns, a watershed drainage area map, and peak-flow-rate calculations comparing pre-development and post-construction conditions, per Sec. 37.09(2).
Can the City require a financial guarantee for stormwater work?
Yes. Sec. 37.09(1)(b) lets the Administrative Authority require a financial security instrument sufficient to guarantee that the stormwater management systems proposed in the plan actually get constructed.
What happens if I skip the stormwater permit?
Conducting a land-disturbing activity that should have had a stormwater management permit carries a $200 forfeiture for a first violation at the site, rising to $500 for a second and $1,000 for a third or subsequent violation, under the fine schedule tied to Sec. 37.06(3).

Sources & Official References

Other rules in Madison

All Madison rules

Compare Madison to another location·View the Wisconsin environmental rules overview

Get notified when Stormwater Management in Madison, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Nearby Cities

How other cities in Dane County handle stormwater management.

Middleton, WI
Some Restrictions
Fitchburg, WI
Some Restrictions
Sun Prairie, WI
Some Restrictions