Monroe Township (Middlesex County), NJ Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Land disturbance trigger
One or more acres
Impervious surface trigger
One-quarter acre or more
Water quality standard
80 percent TSS removal
Water quality design storm
1.25 inches of rainfall in two hours
Groundwater recharge
100% of average annual pre-construction volume
Township's own projects
Covered by the same section

Summary

In Monroe Township, Middlesex County, § 108-5.27 sets minimum stormwater controls for major development: one or more acres disturbed, or one-quarter acre or more of new impervious surface. Projects must remove 80 percent of total suspended solids from new motor vehicle surface runoff.

§ 108-5.27. Stormwater management. ... (2) Purpose. ... The purpose of this section is to establish minimum stormwater management requirements and controls for "major development," as defined below in Subsection B. ... MAJOR DEVELOPMENT (1) An individual development, as well as multiple developments that individually or collectively result in: (a) The disturbance of one or more acres of land since February 2, 2004; ... (17) Stormwater runoff quality standards. (a) This subsection contains the minimum design and performance standards to control stormwater runoff quality impacts of major development. Stormwater runoff quality standards are applicable when the major development results in an increase of one-quarter acre or more of regulated motor vehicle surface. (b) Stormwater management measures shall be designed to reduce the post-construction load of total suspended solids (TSS) in stormwater runoff generated from the water quality design storm as follows: [1] Eighty percent TSS removal of the anticipated load, expressed as an annual average, shall be achieved for the stormwater runoff from the net increase of motor vehicle surface.

Full Breakdown

Section 108-5.27 of the Monroe Township land development chapter applies to major developments in Monroe Township, Middlesex County. Its policy statement says flood control, groundwater recharge and pollutant reduction shall be achieved through stormwater management measures, including green infrastructure best management practices and nonstructural strategies, to maintain natural hydrology and encourage infiltration.

The section applies to nonresidential major developments, to aspects of residential major developments not preempted by the Residential Site Improvement Standards at N.J.A.C. 5:21, and to all major developments undertaken by the Township of Monroe itself. Applications submitted before October 7, 2024 stay under the requirements in effect on October 6, 2024.

Major development is defined as development that results in the disturbance of one or more acres of land since February 2, 2004, the creation of one-quarter acre or more of regulated impervious surface since that date, or the creation of one-quarter acre or more of regulated motor vehicle surface since March 2, 2021. Phased projects that are part of a common plan of development or sale count together.

The design standards are in paragraph D. Every major development needs a maintenance plan for its stormwater measures. Groundwater recharge requires the design engineer to show either that 100% of the average annual pre-construction recharge volume is maintained, or that the increase in runoff volume for the projected two-year storm is infiltrated. For water quality, an increase of one-quarter acre or more of regulated motor vehicle surface triggers 80 percent total suspended solids removal on the net increase, measured against the water quality design storm of 1.25 inches of rainfall in two hours. Stormwater from high pollutant loading areas and industrial stormwater exposed to source material shall not be recharged.

Approvals under the section do not relieve the applicant of other permits, and where another rule is stricter, the more restrictive provision controls. Separate rules for municipal storm sewer systems appear in Chapter 67A.

Violations & Fines

Section 108-5.27 is a condition of development approval, so a major development that does not meet it cannot obtain Planning Board or Zoning Board of Adjustment approval. A variance or a waiver from strict compliance is available only on the showings the section spells out, such as an alternatives analysis for enlarging a public roadway. No separate fine appears in the section.

Frequently Asked Questions

What counts as a major development in Monroe Township?
Development that disturbs one or more acres of land, creates one-quarter acre or more of regulated impervious surface since February 2, 2004, or creates one-quarter acre or more of regulated motor vehicle surface since March 2, 2021. Phased projects under a common plan are counted together under § 108-5.27.
Do single-family house lots have to meet the section?
The section covers nonresidential major developments and only those aspects of residential major developments that are not preempted by the Residential Site Improvement Standards at N.J.A.C. 5:21. Whether a given residential project is covered turns on that preemption and on the major development thresholds.
How much pollution must the stormwater system remove?
Where a project adds one-quarter acre or more of regulated motor vehicle surface, the measures must achieve 80 percent total suspended solids removal of the anticipated load, as an annual average, for runoff from the net increase of motor vehicle surface.
Does the township follow its own rule?
Yes. Section 108-5.27 states that it also applies to all major developments undertaken by the Township of Monroe, in addition to private applicants, so township projects in Monroe Township, Middlesex County must meet the same maintenance plan, recharge and water quality requirements.

Sources & Official References

Other rules in Monroe Township (Middlesex County)

All Monroe Township (Middlesex County) rules

Compare Monroe Township (Middlesex County) to another location·View the New Jersey environmental rules overview

Get notified when Stormwater Management in Monroe Township (Middlesex County), NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.