West New York, NJ Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Plan required
Preliminary grading and drainage plan with every site plan or plat
Reviewer
The Town's Engineers
Runoff limit
110% of existing natural condition
Inlet limit
Five cubic feet per second
Minimum storm pipe
15 inches in diameter
Dry wells
Do not satisfy catch basin requirement

Summary

In the Town of West New York, New Jersey (Hudson County), every site plan or subdivision plat must include a grading and drainage plan that the Town's Engineers can check, and no runoff may be diverted onto neighbors or overload existing drains. Runoff from the site is limited to 110% of its existing natural condition.

Any site plan or land subdivision plat submitted for approval shall be accompanied by a preliminary grading and drainage plan designed to serve the entire property affected and any off-site area contributing runoff at the site in sufficient detail to enable the town's Engineers to determine if the proposal will be an adequate system to carry off, store or discharge the stormwater runoff and the material drainage water originating within and beyond the applicant's property boundaries, including the following: No stormwater runoff or natural drainage water shall be so diverted as to overload existing drainage systems or create flooding or the need for additional drainage structures on other private properties or public lands without approved provisions being made for taking care of such conditions. ... Rainfall runoff from the site shall be limited to 110% of the runoff from the site in its existing natural condition. The town's Engineers shall review all quantities of runoff above this amount directed off-site to determine the applicability of detention and/or retention.

Full Breakdown

Stormwater in the Town of West New York is handled through development review, in Chapter 358, Subdivision of Land, Article VI, Design Standards. Section 358-32 requires any site plan or land subdivision plat submitted for approval to be accompanied by a preliminary grading and drainage plan designed to serve the entire property and any off-site area contributing runoff. The plan has to carry enough detail for the town's Engineers to decide whether it is an adequate system to carry off, store or discharge the runoff and drainage water originating within and beyond the applicant's boundaries. The section also bars diverting stormwater or natural drainage water so as to overload existing drainage systems, flood other private or public land, or create a need for additional drainage structures without approved provisions.

Section 358-33 supplies numbers. Roadways and parking and loading areas need drainage facilities designed to a storm frequency, with pipe systems at 25 years up to 50 acres and the 100-year runoff determined by the rational formula. Inlets restrict runoff to five cubic feet per second so water does not encroach the twelve-foot wide traffic lane. Rainfall runoff from the site is limited to 110% of the runoff in its existing natural condition, and the town's Engineers review anything above that directed off-site to decide whether detention or retention applies.

Section 358-41 covers hardware: all streets get catch basins and pipes, dry wells do not satisfy the requirement, and storm drain pipes have a minimum diameter of 15 inches. Section 358-30B requires a stormwater easement or drainage right-of-way where a watercourse crosses the property. Under § 331-7, unpolluted water such as cooling water cannot be discharged to a community sewer without written approval of the Authority.

Violations & Fines

Chapter 358 prints no stormwater-specific fine. The enforcement tool is approval: a plan the town's Engineers cannot find adequate does not get site plan or subdivision approval, and the developer bears the entire cost of the investigations, tests and designs under § 358-41F(6). The penalty clause in § 358-23, up to $1,000 per lot, concerns lots sold before final subdivision approval, not drainage defects. Discharges of unpolluted water to a sewer without the Authority's approval violate § 331-7.

Frequently Asked Questions

Does a West New York development need a drainage plan?
Yes. Section 358-32 requires any site plan or land subdivision plat submitted for approval to include a preliminary grading and drainage plan serving the entire property and any off-site area contributing runoff, detailed enough for the town's Engineers to judge whether the system is adequate.
How much stormwater runoff can a site release in the Town of West New York?
Section 358-33 says rainfall runoff from the site shall be limited to 110% of the runoff from the site in its existing natural condition. The town's Engineers review quantities above that amount directed off-site to determine whether detention or retention applies.
Can stormwater be sent onto a neighbor's property?
No. Section 358-32 says no stormwater runoff or natural drainage water shall be diverted so as to overload existing drainage systems or create flooding or a need for additional drainage structures on other private properties or public lands without approved provisions.
Can cooling water go into the sewer?
Not without written approval. Section 331-7 bars discharge of unpolluted water, including cooling water, through a direct or indirect connection to a community sewer without written approval of the Authority, which approves it only when no reasonable alternative exists.

Sources & Official References

Other rules in West New York

All West New York rules

Compare West New York to another location·View the New Jersey environmental rules overview

Get notified when Stormwater Management in West New York, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Nearby Cities

How other cities in this county handle stormwater management.

Jersey City, NJ
Some Restrictions