Whitfield County, GA Environmental Rules: Stormwater Management (2026)
Key Facts
- Trigger threshold
- 5,000 sq ft impervious cover or 1 acre disturbed
- Retention standard
- First 1.0 inch of rainfall retained onsite
- Engineer's insurance minimum
- $1,000,000 errors-and-omissions coverage
- Correction deadline
- 30 days' written notice before county acts
- Enforcing officer
- County Building, Zoning and Development Director
- Maximum penalty
- $1,000 fine or 60 days jail (§ 14-8)
Summary
In unincorporated Whitfield County, any new development or redevelopment that creates 5,000 square feet or more of impervious cover, or disturbs one acre or more, must submit a stormwater management plan and hydrology study to the county Building, Zoning and Development Director before construction begins. 'Hotspot' land uses trigger the same review regardless of size, while additions to an existing single-family home are exempt under Section 14-75.
All persons proposing development and/or construction within Whitfield County shall submit a stormwater management plan and hydrology study to the director for review of conformity with this article, except as provided in section 14-75. These standards apply to any new development or redevelopment site meeting one or more of the following criteria: (1)New development that involving the creation of 5,000 square feet or more of impervious cover, or that involves other land development activities of one acre or more;(2)Redevelopment including the creation, addition, or replacement of 5,000 square feet or more of impervious cover, or involving other land development activity of one acre or more;(3)Any new development or redevelopment, regardless of size, defined as a "hotspot" land use;
Full Breakdown
Whitfield County Code Chapter 14, Article VI governs post-development stormwater management for the unincorporated county. Section 14-73 sets the applicability threshold: 5,000 square feet or more of new or replaced impervious cover, one acre or more of land disturbance, any 'hotspot' land use regardless of size, or any phase of a larger common plan of development that reaches those totals. Section 14-75 exempts agricultural and forestry activities, additions to an existing single-family or duplex home, a detached single-family home built outside a larger development, and county-ordered repairs to an existing facility.
Under Section 14-77, an applicant must file a stormwater management plan certified by a Georgia-registered professional engineer, land surveyor, or landscape architect carrying at least $1,000,000 in errors-and-omissions insurance, plus an inspection and maintenance agreement, a performance bond where required, and review fees; projects over 50 lots, ten disturbed acres, or 50 percent impervious coverage need a concept-plan consultation first. 2-inch storm to remove at least 80 percent of total suspended solids, plus 24-hour extended detention of the one-year, 24-hour storm. Section 14-79 requires a recorded maintenance agreement before final plat or certificate of occupancy, with a drainage easement covering the 100-year flood elevation plus ten feet and a 20-foot access easement.
Section 14-80 makes the property owner responsible for maintaining any pre-existing facility, and Section 14-81 gives the county administrator, director, or public works director inspection authority during and after construction.
Violations & Fines
If a private stormwater facility falls out of compliance, the county gives the owner 30 days' written notice to fix it. If the owner does not act, Whitfield County may perform the work itself, bill the owner, and file a lien carrying the same priority as unpaid ad valorem taxes; a partial release requires paying the pro-rata share for the acreage released. Section 14-8 separately makes any Chapter 14 violation a misdemeanor: up to a $1,000 fine, 60 days in jail, or both.
Frequently Asked Questions
Does adding a room to my house in unincorporated Whitfield County need a stormwater permit?
How much impervious surface triggers Whitfield County's stormwater review?
What happens if a private detention pond in Whitfield County is not maintained?
Who signs off on a Whitfield County stormwater management plan?
Sources & Official References
Other rules in Whitfield County
Compare Whitfield County to another location·View the Georgia environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.