Bulloch County, GA Fire Regulations: Propane Storage (2026)
Key Facts
- Governs
- LP-gas on temporary construction-phase RV/camper
- Standard
- Manufacturer's requirements or Uniform codes
- Units per parcel
- One temporary occupancy unit
- Removal deadline
- Within 30 days of certificate of occupancy
- Bond
- Up to $3,000.00 per unit
Summary
Bulloch County's only LP-gas storage rule sits in the zoning ordinance's temporary occupancy unit section, covering the RV or camper a homeowner lives in during construction: its LP-gas storage and delivery system must follow the manufacturer's requirements, or comply with the current Uniform Fire, Building and Mechanical Codes if the manufacturer's specifications are not met.
(j)LP-gas storage and delivery systems shall be maintained in accordance with the manufacturer's requirements. In lieu of complying with the manufacturer's requirements, additional storage of LP-gas is permitted provided the storage and delivery systems comply with the current editions of the Uniform Fire, Building and Mechanical Codes.
Full Breakdown
The county's code does not set a general residential propane tank rule for finished homes; the only county-adopted LP-gas storage standard governs a "temporary occupancy unit" under Zoning Ordinance Section 1445, the recreational vehicle or camper a family or work crew occupies while the permanent house on the same lot is under construction. Section 1445(j) requires that LP-gas storage and delivery systems on that unit be maintained according to the manufacturer's requirements; if the manufacturer's requirements are not followed, the storage and delivery system must instead meet the current editions of the Uniform Fire, Building and Mechanical Codes.
That sits alongside related requirements for the same temporary unit: heating systems and any solid or liquid-fuel burning appliance must also be installed and maintained per the manufacturer's listing, the unit itself must be built to American National Standards Institute (ANSI) code, and no more than one temporary occupancy unit may be occupied per parcel. A separate permit with a fee from the county's schedule of fees is required for the unit, valid for one year with a possible one-year extension if the zoning administrator finds a good-faith construction effort underway, and the unit must come down within 30 days of the certificate of occupancy for the finished home.
00 per unit to guarantee removal, and a code enforcement officer investigating a complaint can demand proof of continuing compliance with these standards or require the occupancy to stop.
Violations & Fines
Failing to maintain the LP-gas storage and delivery system to the manufacturer's requirements or to the Uniform Fire, Building and Mechanical Codes is a violation of Section 1445, and continued noncompliance found during a code enforcement investigation can force the temporary occupancy to cease immediately; general violations of the zoning ordinance are also punishable under Code Section 1-11 with a fine up to $1,000.00, up to 60 days in jail, or both.
Frequently Asked Questions
Does Bulloch County limit propane storage at a regular house?
What standard applies to LP-gas on a temporary occupancy RV?
Can code enforcement check compliance with the LP-gas rule?
Sources & Official References
Other rules in Bulloch County
Compare Bulloch County to another location·View the Georgia fire regulations overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.