Key Facts

AC compressor screening
Required, completely screened
Noise attenuation duty
Baffle noise audible at property line
Screening materials
Match building's predominant façade
Director waiver
Allowed for grade constraints
Occupancy hold
Screening due before certificate of occupancy

Summary

Arvada requires every air conditioning compressor to be completely screened and any rooftop, wall- or ground-mounted mechanical equipment that generates noise perceptible at the street or property line to be baffled or otherwise attenuated to direct the sound upward, under Land Development Code Section 5-1-2-3(A)(10). The rule applies to new development, redevelopment, and building expansions, alongside separate screening standards for vents, flues, and utility meters.

10.Rooftop, Wall Mounted and Ground Mounted Mechanical Equipment, Flues and Exterior Building Elements.a.Screening.i.Rooftop mechanical equipment and appurtenances should all be screened from a public street through the use of parapets or enclosures that are equal to, or greater than, the height of the equipment to be screened....ii.All air conditioning compressors shall be completely screened. Screening enclosures shall use at least one of the predominant materials used in the facades of the primary structure where feasible, and one of the predominant colors used in the primary structure....b.Noise attenuation. Equipment that generates noise perceptible at the adjacent street or property line shall be baffled or otherwise attenuated to direct unavoidable noise upward.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: City Council Policy Manual: Supplement 1 | Code of Ordinances: Supplement 67).

Full Breakdown

Section 5-1-2-3(A)(10) is Arvada's general design standard for rooftop, wall-mounted and ground-mounted mechanical equipment, flues and exterior building elements, applied to all new principal buildings, building façade redesigns, and expansions of gross square footage. Subsection (a)(i) requires rooftop mechanical equipment and appurtenances to be screened from a public street using parapets or enclosures at least as tall as the equipment, built from one of the building's predominant façade materials or colors. Subsection (a)(ii) singles out air conditioning compressors specifically: they must be completely screened, again using the building's predominant materials and colors where feasible.

Wall-mounted utility equipment and meters must be screened from public-street view and painted to blend with the façade under Subsection (a)(iv), and rooftop vents and flues on a pitched roof, or extending above the nearest parapet, must be painted a predominant building color under Subsection (a)(iii). The Director can reduce or waive screening where a substantial grade change makes it impracticable and relocating the equipment is also impracticable. Beyond screening, Subsection (b), 'Noise attenuation,' imposes a separate performance standard: any equipment, including HVAC condensers and compressors, that generates noise perceptible at the adjacent street or property line must be baffled or otherwise attenuated to direct unavoidable noise upward, away from neighboring property and the street.

This noise-attenuation duty applies regardless of whether the screening requirement is met, meaning a fully screened condenser that is still audible off-site is not automatically compliant. Section 8-4-4-3(C)(6) requires screening of roof- and wall-mounted mechanical equipment to be complete before the City signs off on a certificate of occupancy.

Violations & Fines

An unscreened compressor or HVAC unit whose noise carries to the street or a neighboring lot violates Section 10-1-2-1(A)(1) of the LDC and can hold up a certificate of occupancy under Section 8-4-4-3(C)(6). Continued noncompliance after notice exposes the owner to a misdemeanor under Section 10-1-2-3, with a fine up to the Section 1-5 cap of $2,650 and/or 180 days in jail.

Frequently Asked Questions

Does Arvada require AC units to be hidden from view?
Yes. Section 5-1-2-3(A)(10)(a)(ii) requires every air conditioning compressor to be completely screened, using at least one of the building's predominant façade materials and colors where feasible, and the screening must be in place before the City issues a certificate of occupancy.
Is there a rule about how loud my HVAC unit can be?
Section 5-1-2-3(A)(10)(b) requires any mechanical equipment, including HVAC condensers, that generates noise perceptible at the adjacent street or property line to be baffled or otherwise attenuated so unavoidable noise is directed upward, separate from and in addition to the screening requirement.
Can the City waive HVAC screening requirements?
Yes, in limited cases. The Director may reduce or waive screening for a building elevation facing a substantial grade change that makes screening impracticable, but only if relocating the mechanical equipment to a less visible spot is also impracticable.

Sources & Official References

Other rules in Arvada

All Arvada rules

Compare Arvada to another location·View the Colorado noise from specific sources overview

Get notified when HVAC & Mechanical Noise in Arvada, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.