Key Facts
- Adopted code
- Most current National Electrical Code edition, per § 18-570
- Contractor requirement
- City registration plus a valid Colorado electrical contractor's license
- Registration fee
- No fee to process a registration form
- Registration term
- Three years or until the state license expires, whichever is sooner
- Permit lapse
- 180 calendar days without starting work or without inspections
- Work before permit
- Investigation fee plus the required permit fees
- Penalty
- Fine, imprisonment, or both; each day is a separate offense
Summary
Arvada adopts the most current edition of the National Electrical Code as its electrical code, so the edition in force moves whenever NFPA publishes a new one. Electrical contracting in the city requires registration backed by a valid Colorado state electrical contractor's license, and electrical work needs a permit before it starts. Rough electrical is inspected before rough frame.
Class E Electrical License . This license shall entitle the holder to contract for and perform all work involving electrical systems, wiring, installing, and repairing electrical apparatus and equipment for electric light, heat, and power. To be qualified as an electrical contractor, the person, firm, partnership, co-partnership, association or other organization must hold a valid electrical contractor's license issued by the state according to C.R.S. § 12-115-101 et seq. It shall be the responsibility of the applicant to provide evidence of the state license to the city. ... Registration . It shall be unlawful for any person to engage in electrical contracting in the City of Arvada without being duly registered as provided in this chapter. ... Pursuant to C.R.S. § 31-16-101 et seq. and the Arvada City Charter, the most current edition of the National Electrical Code (NEC), as it becomes published by the National Fire Protection Association and as may be updated from time to time, is hereby adopted as the electrical code of the City of Arvada.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: City Council Policy Manual: Supplement 1 | Code of Ordinances: Supplement 67).
Full Breakdown
Section 18-570 adopts the National Electrical Code under C.R.S. § 31-16-101 et seq. and the Arvada City Charter. The wording is open-ended: it takes the most current edition as the National Fire Protection Association publishes it, with no fixed edition year in the section. Section 18-2 backs this up by providing that whenever a technical code references the ICC Electrical Code, the reference means the National Electrical Code most recently adopted by Arvada.
Who can do the work is set by section 18-74. The Class E Electrical License covers all work on electrical systems, wiring, and apparatus for electric light, heat, and power. An applicant must hold a valid electrical contractor's license from the State of Colorado under C.R.S. § 12-115-101 et seq. and must give the city evidence of it. Section 18-74(b) then makes it unlawful to engage in electrical contracting in Arvada without being registered. The Building Safety Division furnishes the registration forms, and no fee is charged to process a registration form. Under section 18-75(a), an electrical registration expires three years from the date of issue or on the expiration date of the state license, whichever is sooner, and an expired registration must be renewed before work in progress is continued or completed.
Other trades cannot stand in for an electrician. The Class D subcontractor license does not authorize any electrical work, and a Class M mechanical contractor must use a city-registered electrical contractor for line voltage electrical work. A registered professional engineer who only plans or designs an electrical installation is not classified as an electrical contractor under the section 18-2 definition. An owner-occupant does not need a contractor's license to work at the owner's own home, but section 18-71(a)(1) requires a permit whenever one is required, and the work must still follow the Code.
Permits and inspections run through the same chapter. Section 18-39(a)(3) makes it unlawful to alter, repair, equip, or maintain a building or structure without first obtaining a required permit. A permit expires if work is not commenced within 180 calendar days or is suspended or abandoned for 180 calendar days under section 18-39(f). The permit holder must post the property so the address is clearly visible from the street before work starts (§ 18-43). For houses built under the International Residential Code, section 18-173 requires a rough mechanical, electrical, and plumbing inspection before the rough frame inspection.
Violations & Fines
Engaging in electrical contracting without registration, starting electrical work without a permit, and using unsafe equipment are all unlawful under section 18-39(a). A conviction carries a fine, imprisonment, or both, up to the limits in section 1-5 of the Arvada City Code, and each day a violation continues is a separate offense. Prosecution begins with a summons and complaint in municipal court under chapter 58. Starting without a permit also adds an investigation fee on top of the permit fees under section 18-42(e). Denial, suspension, or revocation of a license or permit does not count as a penalty, so it can be imposed in addition to a fine.
Frequently Asked Questions
Which edition of the National Electrical Code does Arvada enforce?
Can I wire my own house in Arvada?
What does an electrical contractor need to register with Arvada?
What happens if electrical work starts before the permit is issued?
Can a general or mechanical contractor do the electrical part of a job?
Sources & Official References
Other rules in Arvada
Compare Arvada to another location·View the Colorado building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Electrical Permits in Nearby Cities
How other cities in Jefferson County handle electrical permits.