Arvada, CO Building Safety: Plumbing Permits (2026)
Key Facts
- Adopted code
- 2024 International Plumbing Code with Appendices B, C, and D
- Adopting ordinance
- Ord. No. 4921, adopted March 24, 2026
- Enforcing agency
- Building Safety Division and its code official
- Permit lapse
- 180 calendar days without start or called inspection
- Restart after lapse
- Half the new-permit fee if under one year
- Building sewer depth
- Not less than 36 inches below grade
- Contractor license term
- Class P: three years or state license expiry, whichever is sooner
Summary
Arvada adopts the 2024 International Plumbing Code, with Appendices B, C, and D, through City Code § 18-386 (Ord. No. 4921, adopted March 24, 2026). The Building Safety Division enforces it. A plumbing permit lapses after 180 calendar days without a started job or a called inspection, and violations carry the fine and jail limits of Section 1-5.
Pursuant to C.R.S. § 31-16-101 et seq. and the Arvada City Charter, the International Plumbing Code, 2024 Edition, including Appendices B, C, and D, published by the International Code Council, 4051 Flossmoor Road, Country Club Hills, IL 60478, is hereby adopted by reference and incorporated into the Arvada City Code. The 2024 International Plumbing Code shall be known as the "IPC" or the "plumbing code" and may be cited and referred to as such. ... 105.5.3. Expiration. Expiration of permits shall be as set forth in Sec. 18-39(f). ... 108 Fees. The fees for all plumbing work shall be as set forth in Sec. 18-42. ... 114.4. Violation penalties. Any violation of the plumbing code shall be punishable by a fine, or imprisonment, or both, not to exceed the limits established in Section 1-5 of the Arvada City Code. ... Building sewers that connect to public sewage disposal systems shall be not less than (36) inches (304.8 mm) below grade and shall follow the city of Arvada Engineering Standards where applicable.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: City Council Policy Manual: Supplement 1 | Code of Ordinances: Supplement 67).
Full Breakdown
Section 18-386 adopts the International Plumbing Code, 2024 Edition, published by the International Code Council, including Appendices B, C, and D, and directs that it be called the "IPC" or the "plumbing code." Ordinance No. 4921, adopted March 24, 2026, repealed the old Chapter 18 and enacted the current one, so the 2024 edition is the plumbing standard for work in Arvada. Section 18-387 retitles it the International Plumbing Code of the City of Arvada. Section 18-389 adds that any technical amendment Colorado adopts to the 2024 IPC also applies in Arvada, and the state amendment controls if it conflicts with an Arvada-only change.
The Building Safety Division is the agency, and its head is the code official (§ 18-390). Four administrative sections of the IPC are replaced by pointers into Chapter 18: permit expiration follows § 18-39(f), fees follow § 18-42, appeals follow § 18-36, and penalties follow Section 1-5. The IPC's own extension section (105.5.4) and Board of Appeals section (113) are deleted.
Under § 18-39(f), a permit becomes void if work is not commenced within 180 calendar days of the permit date, or if work is suspended or abandoned for 180 calendar days. A permit counts as suspended or abandoned when 180 calendar days pass and no required inspection is called for. Restarting takes a new permit at one half of the new-permit fee when the plans are unchanged and the lapse has not exceeded one year; after a year the permittee must ask in writing for reactivation and pay full fees. The building official can extend the start time by up to 180 calendar days on a written request showing circumstances beyond the permittee's control.
Under § 18-42, a permit is not valid until fees are paid, and a check or card payment that fails to clear voids the permit. Starting plumbing work before the permit issues triggers an investigation fee on top of the permit fee. Emergency work is excepted only if the division is notified by phone or fax before the end of the next working business day and an application follows within one week.
Arvada also layers local technical rules onto the IPC. Building sewers that connect to the public system must be not less than 36 inches below grade (§ 18-397). The public sewer is treated as unavailable when it sits more than 400 feet from the proposed building (§ 18-406). Unions or an approved disconnect go within 12 inches of each side of regulating equipment and water heaters (§ 18-400).
Violations & Fines
Any person, firm, or corporation convicted of violating Chapter 18 faces a fine, imprisonment, or both, up to the limits in Section 1-5 of the Arvada City Code, for each offense, and each day a violation continues is a separate offense (§ 18-39(b)). Performing plumbing work without a required permit is unlawful under § 18-39(a)(3). Engaging in plumbing contracting without being registered is unlawful under § 18-74(m). Prosecution starts with a summons and complaint in Arvada Municipal Court, and the city can also seek court action to stop or abate the violation.
Frequently Asked Questions
Which plumbing code does Arvada enforce?
How long does an Arvada plumbing permit last?
What happens if I start plumbing work before getting a permit?
Who is allowed to do plumbing work in Arvada?
How do I appeal a plumbing decision by the building official?
Sources & Official References
Other rules in Arvada
Compare Arvada to another location·View the Colorado building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Plumbing Permits in Nearby Cities
How other cities in Jefferson County handle plumbing permits.