Key Facts

Governing section
City Code § 18-39(a)(3)
Permit exemption
Fences 6 ft or under (§18-170)
Permit expiration
180 days unused or abandoned
Issuing office
Building inspection division
Penalty
Fine/imprisonment up to §1-5 limits, per day

Summary

Arvada requires a city building permit before any construction, alteration, repair, or demolition work begins on a building or structure, under Section 18-39 of the City Code. The building inspection division issues permits after plan review and fee payment, and only a short list of minor work, like fences six feet tall or under, is exempt.

It shall be unlawful for any person to erect, construct, enlarge, alter, repair, move, improve, remove, convert, demolish, equip, use, occupy, or maintain any building or structure in the city or cause such to be done contrary to or in violation of any of the provisions of this Code and without first having obtained a permit as required by the provisions of this Code. Permits for work in rights of way shall be in accordance with chapter 78 of the Arvada Code of Ordinances.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: City Council Policy Manual: Supplement 1 | Code of Ordinances: Supplement 67).

Full Breakdown

Section 18-39(a)(3) makes it unlawful to erect, construct, enlarge, alter, repair, move, improve, remove, convert, demolish, equip, use, occupy, or maintain any building or structure in Arvada without first obtaining a permit from the building inspection division; permits for work in the public right of way instead follow Chapter 78. Fees are set by the administrative fee schedule referenced in Section 18-42, and a plan review fee is due when submittal documents are required. Building permit valuations use the higher of the actual contract cost or the ICC Building Valuation Data Chart, adjusted each January 1 by the Denver City Cost Index from RSMeans Data.

Anyone who starts work before a permit issues owes an investigation fee on top of the permit fee, unless the work was genuine emergency work reported to the division by the next business day. C. 2 are unchanged. A permit expires if work has not started within 180 calendar days of issuance, or if work is suspended or abandoned for 180 calendar days, under Section 18-39(f); restarting then costs half the original fee unless the lapse exceeded a year, in which case a full new fee applies.

Violations & Fines

Working without a required permit is a misdemeanor under Section 18-39(b), punishable by a fine or imprisonment, or both, up to the limits in Section 1-5 of the Arvada City Code, with each day of continued work a separate offense. The city may also assess an investigation fee against anyone who begins work before a permit issues, and can institute legal action to restrain or correct unpermitted construction under Section 18-39(c).

Frequently Asked Questions

What work requires a building permit in Arvada?
Section 18-39(a)(3) requires a permit for essentially any construction, alteration, repair, moving, or demolition of a building or structure in the city, obtained from the building inspection division before work begins, with permits for work in city rights of way handled separately under Chapter 78.
Is a permit required to build a backyard fence?
No, as long as the fence is not over six feet high. Section 18-170 amends the residential code's work-exempt list so fences six feet tall or under do not need a building permit; taller fences and the other listed exemptions in R105.2 still apply as written.
What happens if I start construction before getting a permit?
The building official assesses an investigation fee in addition to the required permit fees, and anyone who completes work without ever obtaining a permit can be fined or jailed, or both, under the penalty limits in Section 1-5, with each day treated as a separate violation.

Sources & Official References

Other rules in Arvada

All Arvada rules

Compare Arvada to another location·View the Colorado building safety overview

Get notified when Building Permits in Arvada, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Jefferson County handle building permits.

Lakewood, CO
Some Restrictions