Construction hours in Hollywood, FL, sometimes called construction noise rules or contractor work-hour ordinances, set when contractors can run power tools, hammers, and heavy equipment.

Key Facts

Weekday hours
7:00 a.m. to 6:00 p.m.
Saturday hours
8:00 a.m. to 6:00 p.m.
Sunday
no construction work permitted
Emergency exception
written approval, Chief Building Official
First-offense fine
$100

Summary

Construction, alteration, repair, excavation or demolition work in Hollywood is limited to 7:00 a.m. to 6:00 p.m. Monday through Friday, 8:00 a.m. to 6:00 p.m. Saturday, and is barred entirely on Sundays absent a written exception from the Chief Building Official.

§ 100.05 ADDITIONAL LIMITATION FOR CONSTRUCTION ACTIVITY. The construction, alteration, repair, excavation, or demolition of any building or structure is to be con-ducted no earlier than 7:00 a.m. and no later than 6:00 p.m., Monday through Friday. Such work on Saturdays is to be conducted no earlier than 8:00 a.m. and no later than 6:00 p.m. No such work is to be conducted on Sundays. All such work is to be conducted in the described hours and only after obtaining all appropriate permits and approvals from the City of Hollywood and all other applicable agencies. Should an urgent necessity or emergency condition that requires such work to be conducted outside these hours or on Sunday arise, a request to do so shall be provided in writing to the City's Chief Building Official.

Full Breakdown

Section 100.05 sets the construction noise window citywide: weekday work must run no earlier than 7:00 a.m. and no later than 6:00 p.m., Saturday work is compressed to 8:00 a.m. through 6:00 p.m., and no construction work at all may occur on Sundays. The section requires that all such work also hold every applicable permit and approval from the City of Hollywood and other agencies before it begins. If an urgent necessity or emergency condition requires work outside those hours or on a Sunday, the contractor or owner must submit a written request to the City's Chief Building Official, and the code is explicit that no construction work may proceed outside the stated time limits without the Building Official's prior written approval.

The section works alongside § 100.06, which lets the Director of Development Services grant short-term temporary noise permits, capped at three days, when construction under a valid building permit genuinely cannot comply with the hours or the chapter's decibel limits, provided the contractor uses manufacturer-specified noise baffling and keeps equipment in good repair.

Violations & Fines

Construction noise outside the permitted hours is enforced under Chapter 100's general penalty schedule in § 100.09: up to $100 for a first violation, up to $500 for a second within six months, and up to $1,000 per occurrence for a third or later violation, with each day of continuing work outside the window counted as a separate violation.

Frequently Asked Questions

What time can construction start in Hollywood, FL?
Construction, repair, excavation or demolition work may not begin before 7:00 a.m. Monday through Friday or before 8:00 a.m. on Saturday under City Code § 100.05, and no such work is allowed on Sundays.
Can a contractor get an exception to work later or on Sunday?
Only with prior written approval from the City's Chief Building Official. Section 100.05 requires an urgent necessity or emergency to be shown in a written request before any work outside the stated hours can proceed.
Can a builder get a temporary permit to exceed the construction noise limits?
Yes. Section 100.06(B) lets the Director of Development Services issue a temporary permit of up to three days when work under a valid building permit cannot otherwise comply with §§ 100.02 and 100.04, provided approved noise baffling is used.

Sources & Official References

Other rules in Hollywood

All Hollywood rules

Florida rules heatmap·Compare Hollywood to another location·View the Florida noise ordinances overview

Get notified when Construction Hours in Hollywood, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Construction Hours in Nearby Cities

How other cities in Broward County handle construction hours.

Coral Springs, FL
Some Restrictions
Fort Lauderdale, FL
Some Restrictions
Pembroke Pines, FL
Some Restrictions
Pompano Beach, FL
Some Restrictions