Construction hours in Stratford, CT, sometimes called construction noise rules or contractor work-hour ordinances, set when contractors can run power tools, hammers, and heavy equipment.

Key Facts

Permitted weekday hours
7:00 a.m. to 6:00 p.m., § 142-6(B)(7)
Covers
Erection, excavating, demolition, alteration, repair, street and highway excavation
Emergency permit issued by
Board of Building Commissioners
Emergency permit length
Not to exceed three days
Night construction equipment
Must stay within § 142-5 maximum levels
First offense fine
$100, then $250 and $500

Summary

Stratford Code § 142-6(B)(7) bars erecting, excavating, demolishing, altering or repairing a building, and excavating streets and highways, outside 7:00 a.m. to 6:00 p.m. on weekdays in the Town of Stratford, Connecticut. Urgent public-safety work needs a permit from the Board of Building Commissioners, good for no more than three days.

(6) Noise generated by any construction equipment which is operated during daytime hours, provided that operation of construction equipment during nighttime hours shall not exceed the maximum noise levels as specified in § 142-5. ... (7) Building operations. The erection (including excavating), demolition, alteration or repair of any building, or the excavation of streets and highways, other than between the hours of 7:00 a.m. and 6:00 p.m. on weekdays, except in care of urgent necessity in the interest of public safety and then only with a permit from the Board of Building Commissioners, which permit may be granted for a period not to exceed three days while the emergency continues.

Full Breakdown

The Town Council of the Town of Stratford sets construction hours in Chapter 142 (Noise). Section 142-6(B)(7) declares unlawful the erection (including excavating), demolition, alteration or repair of any building, or the excavation of streets and highways, other than between the hours of 7:00 a.m. and 6:00 p.m. on weekdays. The only exception printed in that paragraph is urgent necessity in the interest of public safety, and then only with a permit from the Board of Building Commissioners, which can be granted for a period not to exceed three days while the emergency continues.

The text names weekdays only, so it sets no weekend start time. The chapter also contains a separate exemption in § 142-5(E)(6) for noise generated by construction equipment operated during daytime hours, provided that operation of construction equipment during nighttime hours does not exceed the maximum noise levels in § 142-5. Section 142-3 defines daytime hours as 8:00 a.m. to 8:00 p.m. Monday through Friday, with different Saturday and Sunday hours and a 9:00 p.m. end during daylight savings time, so the two provisions use different clocks and the code does not reconcile them in text.

Section 142-3 defines construction as site preparation, assembly, erection, substantial repair, alteration or similar action, excluding demolition, and construction equipment as equipment operated by fuel or electric power used in construction or demolition work. Emergency work needed to restore property to a safe condition is exempt under § 142-5(E)(1). The Director of Health handles measurements under § 142-9 and can grant variances under § 142-11.

Violations & Fines

Under § 142-10(A) a violation is fined $100 for a first offense, $250 for a second offense within one year of the first, and $500 for each subsequent offense within one year. A violation that continues or repeats more than 30 minutes after a cease order is a separate offense, each day after the correction time is another, and the Town can seek a court order to cease or abate.

Frequently Asked Questions

What hours can construction run in Stratford?
Section 142-6(B)(7) permits building erection, excavating, demolition, alteration and repair, and street and highway excavation, between 7:00 a.m. and 6:00 p.m. on weekdays. The paragraph prints no weekend hours. Outside that window the work is unlawful unless an emergency permit has been issued.
Can work continue after hours in an emergency?
Only in a case of urgent necessity in the interest of public safety, and then only with a permit from the Board of Building Commissioners. The permit can be granted for a period not to exceed three days while the emergency continues. Section 142-5(E)(1) separately exempts noise created as a result of an emergency.
Does the daytime equipment exemption change the hours?
Section 142-5(E)(6) exempts noise from construction equipment operated during daytime hours, which § 142-3 defines as 8:00 a.m. to 8:00 p.m. on weekdays, and requires nighttime operation to stay within the § 142-5 maximum levels. The § 142-6(B)(7) hours are printed separately, and the code does not say how the two interact.
What is the penalty for early or late construction work?
Section 142-10(A) fines $100 for a first offense, $250 for a second within one year of the first, and $500 for each later offense within one year. A violation continuing more than 30 minutes after a cease order is a separate offense, and each uncorrected day counts again.

Sources & Official References

Other rules in Stratford

All Stratford rules

How Stratford compares: Cities with the Strictest Construction Hours·Compare Stratford to another location·View the Connecticut noise ordinances overview

Get notified when Construction Hours in Stratford, CT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.