Issaquah, WA Parking Rules: EV Charging (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified November 2026

Key Facts

Governing section
Issaquah Land Use Code 18.604.090
Small-lot exception
Under 10 spaces, except Group A, E and M occupancies
New homes, two units or fewer
1 EV-ready space per dwelling unit
Other new Group R buildings
10% EVSE, 30% EV-ready, 10% EV-capable
New nonresidential buildings
10% of total parking spaces in each category
Affordable housing at or below 80% AMI
Full requirement, cost neutral, never below 50 percent
Penalty route
Chapter 8.45 IMC civil enforcement

Summary

Issaquah requires new buildings, substantial improvements, new paved surface parking lots and new parking garages to provide electric vehicle charging infrastructure under Land Use Code 18.604.090. Required counts are percentages of total parking spaces set in one residential table and one nonresidential table, and lots with fewer than 10 spaces are excused except for Group A, E and M occupancies.

B. Standards. ... Electric vehicle charging infrastructure must be provided for new and substantial improvements or additions, new surface parking lots (not gravel), and new parking garages as follows: 1. Electric vehicle infrastructure must be provided according to Tables 18.604.090(A) and 18.604.090(B). ... 2. Exception for On-Site Parking With Less Than 10 Spaces. Except for Group A, Group E, and Group M occupancies, on-site parking with less than 10 parking spaces shall not be required to comply with subsection B of this section. ... Table 18.604.090(A). Residential Electric Vehicle (EV) Charging Infrastructure Use Number of EVSE Parking Spaces Number of EV-Ready Parking Spaces Number of EV-Capable Parking Spaces New residential buildings that do not contain more than two dwelling units None 1 per dwelling unit None All other new residential buildings (Group R occupancies) 10% of total parking spaces 30% of total parking spaces 10% of total parking spaces

Full Breakdown

Section 18.604.090 applies to new and substantially improved buildings and additions, new surface parking lots that are not gravel, and new parking garages. Each project must meet three separate counts: electric vehicle supply equipment (EVSE) spaces, electric vehicle ready (EV-ready) spaces and electric vehicle capable (EV-capable) spaces. A mixed-use development splits the test: parking tied to residential uses follows Table 18.604.090(A), and parking tied to nonresidential uses follows Table 18.604.090(B).

For residential parking, a new building with no more than two dwelling units needs no EVSE spaces, 1 EV-ready space per dwelling unit and no EV-capable spaces. All other new Group R buildings need 10% of total parking spaces as EVSE, 30% as EV-ready and 10% as EV-capable. An existing multifamily building (R-1, R-2 and I-2 occupancies) undergoing substantial improvement needs 10% EVSE and 20% EV-ready, with no EV-capable requirement. For nonresidential parking, new Group A, B, E, F, H, I, M and S buildings need 10% of total parking spaces in each of the three categories, existing buildings in those groups under substantial improvement need 5% EVSE and 10% EV-ready, and new surface lots and garages carry a 10% figure in each column.

When EVSE or EV-ready spaces are required, 10 percent of the accessible parking spaces, rounded to the next whole number, must be EVSE, with an additional 10 percent EV-ready, and at least one of each type must be accessible. Every EVSE space needs designated signage and pavement markings per RCW 46.08.185. Wiring must follow the National Electrical Code (NFPA 70), and each EV-ready branch circuit must be identified as "Electric Vehicle Ready" in the service panel or subpanel directory, with the termination location marked the same way.

Projects with affordable housing units at or below 80 percent AMI must meet 100 percent of the requirement, but the cost must stay neutral, and the provision can never drop below 50 percent of the required EVSE, EV-ready and EV-capable infrastructure. Middle housing within one-half mile of a major transit stop is exempt under RCW 36.70A.635(6)(d). The section does not change the minimum or maximum number of off-street parking spaces set elsewhere in the chapter.

Violations & Fines

Violations of the Land Use Code are civil violations enforced under Chapter 8.45 IMC (LUC 18.108.010). The Code Enforcement Officer, authorized by the Mayor, can issue a civil infraction heard in Issaquah Municipal Court, with penalties up to the amounts in Chapter 1.06 IMC, or a notice of violation and order carrying a cumulative $250.00 per day from the compliance date. A repeat violation within 2 years can draw up to $500.00 per day.

Frequently Asked Questions

Does a new house in Issaquah have to include EV charging?
A new residential building with no more than two dwelling units must provide 1 EV-ready parking space per dwelling unit. Table 18.604.090(A) lists None for both EVSE and EV-capable spaces for that building type. The EV-ready branch circuit must be identified as "Electric Vehicle Ready" in the service panel or subpanel directory, and its termination location must be marked.
Do small parking lots have to comply?
On-site parking with fewer than 10 parking spaces is excused from subsection B, except for Group A, Group E and Group M occupancies. Those three occupancy groups must either apply the requirement to designated employee parking only, or provide one EV-ready space and one EV charging station for each 200 parking spaces or fraction thereof, whichever is greater.
Do gravel parking lots need EV infrastructure?
The standard covers new surface parking lots described as "not gravel," along with new parking garages and new or substantially improved buildings. A new gravel surface lot is therefore outside the lot trigger in subsection B, although a building project on the same site can still trigger the tables on its own.
Do EV spaces change how many parking spaces are required?
No. Subsection B.5 states that nothing in the section modifies the minimum number of off-street motor vehicle parking spaces required for specific uses, or the maximum number allowed, in Chapter 18.604. The EVSE, EV-ready and EV-capable counts are percentages of the total parking spaces, and they sit inside the parking supply.
What happens with affordable housing projects?
Projects with units at or below 80 percent AMI must meet 100 percent of the EVSE, EV-ready and EV-capable requirement, provided the cost is neutral. The applicant must show how cost neutrality was calculated, and may propose reduced required parking or reduced parking lot landscaping. Provision cannot fall below 50 percent of the required infrastructure.

Sources & Official References

Other rules in Issaquah

All Issaquah rules

Compare Issaquah to another location·View the Washington parking rules overview

Get notified when EV Charging in Issaquah, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

EV Charging in Nearby Cities

How other cities in King County handle ev charging.

Auburn, WA
Some Restrictions
Federal Way, WA
Some Restrictions
Kent, WA
Some Restrictions
Kirkland, WA
Some Restrictions
Seattle, WA
Some Restrictions