Livermore, CA Parking Rules: EV Charging (2026)
Key Facts
- Governing code
- LMC Ch. 15.38 (Ord. 2060, 2017)
- State authority
- Gov. Code § 65850.7 (AB 1236)
- Review type
- Expedited, nondiscretionary checklist review
- Electronic submittal
- Email, internet or fax accepted
- HOA approval
- Cannot be required as a permit condition
- Use permit trigger
- Written finding of specific adverse impact
Summary
Livermore Municipal Code Chapter 15.38 requires the building official to run an expedited, streamlined permitting process for electric vehicle charging stations under Government Code § 65850.7, using an adopted checklist and barring HOA approval as a condition of the permit.
In the technical review of a charging station, consistent with Government Code Section 65850.7, the building official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by Civil Code Section 4080.
Full Breakdown
38 defines a "charging station" as any level of electric vehicle supply equipment built to Article 625 of the California Electrical Code that delivers power from an outside source into a plug-in electric vehicle. 030 requires the building official to adopt a checklist referencing the Governor's Office of Planning and Research's "Plug-In Electric Vehicle Infrastructure Permitting Checklist," published on the City's website. 040, an applicant must first verify the installation will not create a specific, adverse impact on health, safety or building occupants, covering electrical capacity and loads, wiring, bonding, overcurrent protection, and affected building infrastructure.
A permit application meeting the adopted checklist must be deemed complete and promptly processed; the building official must accept electronic submittal and electronic signatures in lieu of a wet signature. An incomplete application triggers a written correction notice detailing all deficiencies. 050 allows the City to require a use permit only where the building official finds, based on substantial evidence, a specific adverse impact on public health or safety, and expressly bars conditioning approval of any EV charging permit on approval by a homeowners' association as defined in Civil Code § 4080. 060), be incorporated into electrical load calculations as a continuous load, and meet Building or Residential Code anchorage requirements without adversely affecting building elements.
Violations & Fines
Approval of the permit does not authorize energizing or using the charging station until final City approval is granted; unauthorized use before that approval, or installation that skips the load-calculation and anchorage requirements of § 15.38.060, exposes the installer to code enforcement action and correction orders from the building official, who retains authority over higher-priority life-safety situations under § 15.38.050(A).
Frequently Asked Questions
Can my Livermore HOA block my EV charger permit?
What must I verify before applying for an EV charger permit in Livermore?
Does an approved EV charging permit let me start using the charger right away?
Sources & Official References
Other rules in Livermore
California rules heatmap·Compare Livermore to another location·View the California parking rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
EV Charging in Nearby Cities
How other cities in Alameda County handle ev charging.