Weston, FL Property Maintenance: Property Blight (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Enforcing agency
City of Weston Building Official
Unoccupied trigger
60 days triggers mandatory sealing and securing
Continuing violation
Each day is a separate citable offense
Notice method
Certified mail to owner, posted on structure
Governing law
Weston Code of Ordinances Chapter 130
Related process
Minimum Housing cases go to Special Magistrate

Summary

In the City of Weston, Florida, Chapter 130 of the Code of Ordinances lets the Building Official order repair, closure or demolition of any structure that wear, neglect or misuse has made unsafe, unstable or a public nuisance. Owners must prevent and correct these conditions, buildings left vacant 60 days must be sealed shut, and each day a violation continues is a separate citable offense.

§ 130.01 PURPOSE. The Unsafe Structures Chapter is established to provide standards and requirements for maintenance, repair, closure, disposition and demolition of Structures or Premises that have, through wear, neglect or use, become unsafe, unstable or a nuisance to occupants of the Structures or the public at large. ... § 130.05 UNOCCUPIED BUILDINGS. Unoccupied Buildings are Buildings that have not been occupied or used for a period of 60 days. Owners of unoccupied Buildings shall seal off, secure and maintain as secured all entrances and openings to the Building . ... § 130.06 UNSAFE STRUCTURES. 130.06(A) Owners shall prevent Structures from becoming unsafe. ... 130.06( ... C) A Structure shall be deemed unsafe if: 130.06(C)(1) There is substantial accumulation of Debris or other combustible materials therein; ... 130.06(C)( ... 5) The Structure , or any part thereof, is partially destroyed; ... § 130.0 ... 7 SEPARATE AND DISTINCT OFFENSES. 130.07(A) Continuing violations. Each day a condition continues after the initial citation for the condition shall be considered a separate and distinct citable offense.

Full Breakdown

Weston's Unsafe Structures Chapter, Chapter 130 of the Code of Ordinances, targets structures and premises that wear, neglect or misuse have turned unsafe, unstable or into a public nuisance, and it separately covers buildings that sit unoccupied for a significant period (§ 130.01). Under § 130.06(A) and (B), owners must prevent their structures from becoming unsafe and must correct any physical condition that renders a structure unsafe, following the standards in the Florida Building Code and the City Code. Section 130.06(C) lists the conditions that make a structure legally unsafe: a substantial accumulation of debris or combustible material, a hazard to fire-safety ingress or egress, loosening siding, block, brick or roof tiles, deterioration of load-bearing or roof members, partial destruction, interior water damage that compromises structural integrity, sagging or out-of-plumb framing, deteriorated electrical or mechanical systems, damaged plumbing creating unsanitary conditions, toxic mold contamination, or the absence of an approved potable water supply.

The Building Official may also declare a structure unsafe on a case-by-case finding that wear, neglect or misuse has weakened its structural integrity (§ 130.06(D)). Section 130.05 requires owners of buildings unoccupied for 60 days to seal off and secure every entrance and opening. Enforcement runs through the Building Official (§ 130.08), and § 130.07 treats each day a violating condition continues past the initial citation as a separate, distinct citable offense, while an owner may be cited separately for every condition that renders the structure unsafe.

Related Minimum Housing and Unsafe Structures cases proceed to the Special Magistrate or the Unsafe Structures Board under § 31.09, with written notice sent by certified mail to the record owner, addressed to 'Occupant' by U.S. Mail, and posted conspicuously on the structure itself.

Violations & Fines

Weston's Building Official enforces Chapter 130 directly, and each day an unsafe condition continues past the citation deadline counts as a new, separately citable offense under § 130.07(A); an owner can also be cited once for every distinct unsafe condition on the same structure under § 130.07(B). Notice of Minimum Housing or Unsafe Structures violations must go by certified mail to the owner of record, by U.S. Mail addressed to 'Occupant,' and be posted on the property itself per § 31.09(B).

Frequently Asked Questions

What makes a structure 'unsafe' under Weston's code?
Under § 130.06(C), a structure is deemed unsafe if it has a substantial buildup of debris or combustible material, a fire-safety hazard at an exit or entrance, loosening siding, block or roof tiles, damaged load-bearing or roof members, partial destruction, structural water damage, sagging framing, failing electrical, mechanical or plumbing systems, toxic mold, or no approved potable water supply.
How long can a building sit vacant before Weston requires it to be secured?
Section 130.05 defines an unoccupied building as one that has not been used for 60 days. Once that threshold passes, the owner must seal off, secure and keep secured every entrance and opening to the building, regardless of whether the structure is otherwise found unsafe under § 130.06.
Who enforces Weston's Unsafe Structures Chapter and how are owners cited?
The Building Official enforces Chapter 130 under § 130.08. Section 130.07 treats each day an unsafe condition continues past the citation date as a separate offense, and the owner can be cited separately for every distinct condition rendering the structure unsafe, so multiple violations can stack on one property.
Does Weston have to notify the property owner before acting on an unsafe structure?
Yes. Under § 31.09(B), notice for Minimum Housing and Unsafe Structures cases must be sent by certified mail to the record owner listed with the Broward County Property Appraiser, mailed to 'Occupant' at the property address, and posted in a conspicuous place on the structure itself.

Sources & Official References

Other rules in Weston

All Weston rules

Florida rules heatmap·Compare Weston to another location·View the Florida property maintenance overview

Get notified when Property Blight in Weston, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Property Blight in Nearby Cities

How other cities in Broward County handle property blight.

Coral Springs, FL
Some Restrictions
Fort Lauderdale, FL
Significant Restrictions
Hollywood, FL
Significant Restrictions
Miramar, FL
Significant Restrictions
Pembroke Pines, FL
Some Restrictions
Pompano Beach, FL
Significant Restrictions