Bulloch County, GA Sidewalk & Pedestrian Rules: Encroachment Permits (2026)
Key Facts
- Permit required for
- Excavation, alteration, driveway construction in ROW
- Governing sections
- Bulloch County Code §§ 11.5-30, 11.5-32
- Application filed with
- County engineer, in writing
- Application fee
- Nonrefundable, per county fee schedule
- Security
- Bond/letter of credit valid 1 year after completion
Summary
Digging into, altering, or building a driveway across a public right-of-way in unincorporated Bulloch County requires a county permit first. Sec. 11.5-30 makes unpermitted excavation and unpermitted private-road or driveway construction in the right-of-way unlawful, and Sec. 11.5-32 requires a written application and nonrefundable fee before the county engineer will issue one.
(3)It shall be unlawful for any person, without a permit issued by the county, to purposely excavate or alter the surface, shoulders or sides of any public road, street, sidewalk or other public passage. ... (5)In order to aid in the proper drainage of water and prevent erosion on the public roadways of this county, it shall be unlawful for any person to construct within a public right-of-way a private road or driveway for ingress and egress onto one's property without first obtaining a permit through the office of the county manager or his designee and paying such fees as may be required for the purchase and installation of concrete pipe as necessary to ensure the unobstructed flow and drainage of water within such public rights-of-way. ... A nonrefundable fee for the application shall be set forth in the county schedule of fees and charges.
Full Breakdown
§ 32-1-1), covers every publicly maintained road, street, sidewalk, curb, gutter, drainage inlet, manhole, water valve and survey benchmark in the unincorporated county, aside from state highways and private roads. Sec. 5-30(a)(3) makes it unlawful for anyone, without a county-issued permit, to purposely excavate or alter the surface, shoulders or sides of a public road, street, sidewalk or other public passage. Sec. 5-30(a)(5) separately targets driveways: building a private road or driveway for ingress and egress within a public right-of-way, without first getting a permit from the county manager's office and paying the fees needed to install the concrete pipe required to keep drainage flowing, is unlawful, though the county engineer or transportation director can waive the pipe requirement if it isn't needed for drainage.
To get either permit, Sec. 5-32 requires the applicant to file a written application with the county engineer describing the nature, extent, location and timing of the proposed work, pay a nonrefundable application fee set by the county's schedule of fees and charges, and, at the county engineer's discretion, post a bond or letter of credit sized to the estimated repair cost, good for one year after the work is finished. Work must also follow Georgia DOT traffic-control and roadbed standards under Sec. 5-31, and anyone caught working outside the area their permit actually covers can be hit with a stop-work order or a citation from a code enforcement officer or the Sheriff's Office, returnable to Magistrate Court.
Violations & Fines
Excavating, altering or building a driveway in the county right-of-way without the Sec. 11.5-30 permit is unlawful, and working outside the area a permit actually covers under Sec. 11.5-30(a)(7) can bring a stop-work order plus a citation from a code enforcement officer or the Bulloch County Sheriff's Office, returnable to the Magistrate Court of Bulloch County.
Frequently Asked Questions
Do I need a permit to build a driveway that crosses the county right-of-way?
What does the county require before issuing a right-of-way permit?
What happens if I dig up the right-of-way without a permit?
Sources & Official References
Other rules in Bulloch County
Compare Bulloch County to another location·View the Georgia sidewalk & pedestrian rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.