Key Facts

Permit issuer
City engineer, who may approve or reject at absolute discretion
Basic encroachment fee
$25.00 base fee
Street encroachment fee
$100.00 base fee
Extra fee
$0.50 per linear foot beyond 25 linear feet of disturbance
Permit expiry
30 days basic, 60 days street, 30-day extensions
Minimum surety bond
$500.00 per single permit, waived for residential sidewalk repair

Summary

Anyone in Georgetown who plans to excavate, tear up, repair, obstruct or lay materials on a street, sidewalk, public easement or other right-of-way must first apply to the city engineer for an encroachment permit. The base fee is $25.00 for work that stays out of the street and $100.00 for street encroachments, and the city engineer has absolute discretion to approve or reject.

(b) Any person, firm, corporation, or association planning to excavate, tear up, repair, obstruct or lay materials on any street, sidewalk, public easement or other public right-of-way in the city for any purpose, including, but not confined to, the laying of water, gas or sewer lines or connections, shall first apply to the city engineer for an encroachment permit and shall state the nature, extent, and time period for completion of the proposed work. The base fee associated with the encroachment permit shall fall under one of the following categories: (1) Basic encroachment fee. A $25.00 base fee will be assessed for permits acquired for the purpose of encroachments other than those that extend into the street; this shall include, but is not limited to, sidewalk repairs, fence construction, and construction in an easement. (2) Street encroachment fee. A $100.00 base fee will be assessed for permits acquired by public utility companies, subcontractors working at the direction of public utility companies, or home/property owners repairing utilities that extend into the city's street.

View official code

Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 4).

Full Breakdown

Section 32-76 of the Georgetown Code requires a permit before any person, firm, corporation or association excavates, tears up, repairs, obstructs or lays materials on a street, sidewalk, public easement or other public right-of-way, for any purpose. Laying water, gas or sewer lines is named as an example, not a limit. The applicant states the nature, extent and time period for completion of the work. The city engineer creates the application form and can require additional documentation.

There are two base fee categories. The basic encroachment fee is $25.00 for encroachments that do not extend into the street, and the code lists sidewalk repairs, fence construction and construction in an easement. The street encroachment fee is $100.00 for permits obtained by public utility companies, subcontractors working at a utility's direction, or home and property owners repairing utilities that extend into the city's street. The base fee rises by $0.50 per linear foot for each linear foot of disturbance beyond 25 linear feet.

Timing rules are specific. A basic permit expires 30 days after issuance and a street encroachment permit expires 60 days after issuance. The city engineer can extend either one by 30 days for good cause, and after the extension the permittee applies for a new permit. Applications are due at least three business days before the target start date, or ten business days for street cut work, subject to the emergency repair exceptions in section 32-81. If someone other than the owner does the work, the contractor submits the application. City, county, state and federal agencies get a fee waiver but remain bound by every other requirement, including the bond.

Section 32-78 adds a surety bond for cuts or excavations other than a sidewalk in a residential area. The minimum is $500.00 for a single permit, set by the city engineer from the estimated restoration cost. The bond is returned one year after final inspection and approval. Regular excavators can instead deposit a running bond set at a minimum of $50,000.00 covering one year. No bond is required for repairing or replacing a sidewalk on residentially zoned property.

Violations & Fines

Violations of the street restoration article are civil offenses under section 32-88, enforced by the code enforcement board, hearing officers, code enforcement officers and citation officers, and all are Class 2 violations. Under section 2-842 the initial fine is $100.00, with $100.00 added for each seven days beyond the remediation date until the total reaches $1,000.00. A contested citation carries a maximum civil fine of $2,000.00 per violation. Penalties are waived only if the same or similar violation has not occurred on the property or by the same permittee within the calendar year and it is remedied in the time the officer specifies.

Frequently Asked Questions

Do I need an encroachment permit to repair my own sidewalk in Georgetown?
Yes. Section 32-76 requires a permit to repair or obstruct any sidewalk or right-of-way, and it lists sidewalk repairs under the $25.00 basic encroachment fee. Section 32-78(f) says no bond is required when the project repairs or replaces a sidewalk on residentially zoned property, but the rest of the article still applies.
How far in advance must I apply?
At least three business days before the target start date of construction. Street cut work needs ten business days. These notice periods are subject to the emergency repair exceptions in section 32-81. If a contractor does the work instead of the owner, the contractor submits the application.
How long does an encroachment permit last?
A basic encroachment permit expires 30 days after issuance and a street encroachment permit expires 60 days after issuance. The city engineer can extend either for good cause in his sole discretion, and each extension is 30 days. After that, the permittee must apply for a new permit to finish the work.
What does the street encroachment fee cover?
The $100.00 base fee applies to permits obtained by public utility companies, subcontractors working at a utility's direction, or home and property owners repairing utilities that extend into the city's street. Disturbance beyond 25 linear feet adds $0.50 for each additional linear foot.
Can the city refuse my permit?
Yes. Section 32-76(h) says the city engineer, in his absolute discretion, keeps the authority to approve or reject encroachment permit applications. Government agencies are exempt from the application fee but not from the bond or the other requirements in the article.

Sources & Official References

Other rules in Georgetown

All Georgetown rules

Compare Georgetown to another location·View the Kentucky sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Georgetown, KY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.