Key Facts
- Short-term permit
- Encroachments of 90 days or less
- Long-term permit
- Encroachments over 90 days
- Example long-term use
- Building overhangs, footings
- Recording
- License may record at county
Summary
Gresham requires an encroachment permit for temporary facilities, stored materials, or minor construction placed in the public right-of-way in front of a property.
(d) An encroachment permit will be required for placing temporary facilities in the public right-of-way and for certain minor activities in the public right-of-way:
(i) A short-term encroachment permit will be required for placing temporary facilities and storing materials in the public right-of-way for 90 days or less; for work involving planting, trimming, and placing of trees in the public-right-of-way; and for work in rights-of-way that does not alter the ground surface or public infrastructure.
(ii) A long-term encroachment permit will be required for encroachments expected to be greater than 90 days, such as building overhangs and footings placed in the public right-of-way. In addition to a long-term encroachment permit, the Manager may require the applicant to enter into a license to encroach which shall be recorded on the benefitting property at the Multnomah County Recorder's Office.
Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.
Full Breakdown
Under GRC Article 6.35, no one may store materials or place facilities in a Gresham public right-of-way without a permit. A short-term encroachment permit covers temporary facilities, stored materials, or tree work in the right-of-way for 90 days or less; encroachments expected to last longer, such as building overhangs or footings, need a long-term encroachment permit and may require a recorded license to encroach.
Violations & Fines
Placing materials, structures, or building elements in the right-of-way without the required encroachment permit can draw a stop-work order, permit denial, and removal of the encroachment at the responsible party's expense under GRC Article 7.50.
Frequently Asked Questions
Do I need a permit to store a moving pod at the curb in Gresham?
How long does a Gresham encroachment permit last?
Sources & Official References
Other rules in Gresham
Compare Gresham to another location·View the Oregon sidewalk & pedestrian rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Encroachment Permits in Nearby Cities
How other cities in Multnomah County handle encroachment permits.