Summary

Idaho Falls requires a City Engineer permit before any private construction, repair, or excavation in a street, alley, easement, or other public right-of-way, including sidewalks and driveways.

No person shall engage in any construction, repair or

excavation in any street, alley, easement or other public right-of-way within the City without

first obtaining a permit to do so approved by the City Engineer. Engaging in any such

construction, repair, or excavation without a permit shall constitute an infraction. No permit

under this Chapter shall be valid until or unless the notice provisions of Idaho's Underground

Facilities Damages Prevention Act have been complied with. The permit shall clearly define the

area within which the permittee may do such construction, repair or excavation. A copy of the

permit shall be kept on file with the City Engineer for a period of not less than ten (10) years

after acceptance of the completed work that was permitted. The permittee shall keep a copy of

the permit onsite at all times that work under this permit is being performed. (Ord. 2970, 11-25-

14)

Full Breakdown

Idaho Falls City Code section 8-7-2 bars anyone from constructing, repairing, or excavating in a street, alley, easement, or other public right-of-way, including paving, sidewalks, driveways, curbs, and utility lines, without a permit approved by the City Engineer. Doing the work without one is an infraction. The permit must define the approved work area, the applicant must comply with Idaho's Underground Facilities Damage Prevention Act notice requirements, and a copy must stay on site while work is underway; the City keeps its own copy on file for at least ten years.

Violations & Fines

Working in the public right-of-way without a permit is an infraction under section 8-7-2, and the City Engineer can revoke or suspend permits or a contractor's license for noncompliance.

Frequently Asked Questions

Do I need a permit to dig in the street or sidewalk right-of-way in Idaho Falls?
Yes. City Code section 8-7-2 requires a City Engineer-approved permit before any construction, repair, or excavation in a street, alley, easement, or public right-of-way.
What happens if I do right-of-way work without a permit?
It's an infraction under section 8-7-2, and the City can also revoke your right-of-way contractor's license or existing permits under section 8-7-13.

Sources & Official References

Other rules in Idaho Falls

All Idaho Falls rules

Compare Idaho Falls to another location·View the Idaho sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Idaho Falls, ID changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.