Key Facts

Governing section
KCC 6.06.020
Permit issuer
Dept. of Public Works
Permit validity
Expires 90 days if unstarted
Warranty period
2 years after final inspection
Unpermitted work penalty
Doubled permit fee
Criminal penalty
Misdemeanor, separate offense per day

Summary

Anyone who wants to cut into a Kent street or curb, most often to install a driveway or connect a utility line, must first get a separate right-of-way permit from the department of public works under KCC 6.06.020. Each cut needs its own permit.

No person shall cut a street or curb without first obtaining a separate right-of-way permit for each cut of a street or curb from the department of public works. ... It is unlawful for any person, firm, or corporation to cut a street or curb, or cause the same to be done, in violation of any of the provisions of this chapter. Any person, firm, or corporation violating any of the provisions of this chapter, upon conviction, shall be guilty of a misdemeanor. Each such person shall be guilty of a separate offense for each and every day or portion thereof during which any violation of any of the provisions of this chapter is committed, continued, or permitted.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 4542, passed June 16, 2026).

Full Breakdown

KCC 6.06.020 sets the baseline rule: no person shall cut a street or curb without first obtaining a separate right-of-way permit for each cut of a street or curb from the department of public works. The permit application, required by KCC 6.06.030, must identify the contractor or subcontractor performing the work, that contractor's state contractor registration number and city business license number, describe the work and its location, and be signed by the property owner or the performing firm's agent. Before the city issues the permit, KCC 6.06.040(A) requires that a city official first inspect and approve the proposed cut location, and KCC 6.06.040(C) gives the permit a 90-day shelf life: it expires if work has not started within that window unless it is extended.

Once work begins, KCC 6.06.060 requires the permittee to restore the street or curb to its original or better condition, including any needed overlay, and holds the permittee responsible for defects in the cut area for two full years after final inspection. The director can impose special conditions case by case, including approved traffic control devices, keeping at least one travel lane open, maintaining ingress and egress to abutting property, and posting a surety indemnity bond and liability insurance naming the city as an additional insured. Cutting without first obtaining the permit does not excuse compliance: KCC 6.06.050(C) doubles the basic permit fee for work started without one.

Violations & Fines

KCC 6.06.070 makes it unlawful to cut a street or curb, or cause the cut to be done, in violation of any chapter requirement, and any conviction is a misdemeanor. The section treats each day a violation continues as a separate offense, so an unpermitted or noncompliant cut left unresolved can generate a new misdemeanor charge daily until it is corrected, on top of the doubled permit fee KCC 6.06.050(C) imposes for work performed before a permit issues.

Frequently Asked Questions

Do I need a city permit to cut my own curb for a new driveway in Kent?
Yes. KCC 6.06.020 requires a separate right-of-way permit from the department of public works for each street or curb cut, and the location must be inspected and approved by the city before the permit issues.
How long is a Kent curb cut permit good for?
KCC 6.06.040(C) gives the permit a 90-day life from issuance; if work has not begun by then and the permit has not been extended, it expires and a new application is required.
What if a contractor cuts a Kent street before getting the permit?
KCC 6.06.050(C) doubles the basic permit fee for work started without one, and KCC 6.06.070 makes the unpermitted cut a misdemeanor, with each day the violation continues charged as a separate offense.

Sources & Official References

Other rules in Kent

All Kent rules

Compare Kent to another location·View the Washington sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Kent, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Nearby Cities

How other cities in King County handle encroachment permits.

Renton, WA
Some Restrictions
Auburn, WA
Some Restrictions
Bellevue, WA
Some Restrictions
Federal Way, WA
Some Restrictions
Kirkland, WA
Significant Restrictions
Seattle, WA
Significant Restrictions