Kissimmee, FL Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit required for
Facilities and excavation in ROW
Bond
At least 150% of repair cost
Also requires
Proof of liability insurance
Adopted
Ord. No. 2982, July 3, 2018

Summary

Kissimmee requires a city manager permit before anyone builds, excavates, or installs facilities in a public right-of-way, conditioned on an application, site restoration, fees, a bond of at least 150% of repair costs, and liability insurance.

No facilities shall be erected on city rights-of-way except by easements or license. Any construction planned on the city rights-of-way shall not be constructed unless a permit is first obtained from the city manager or his designee. The issuance of permits for the construction, maintenance and operation of facilities within city rights-of-way or facilities which require excavation within city rights-of-way in order to be constructed, maintained or operated on the surface or overhead shall be conditioned upon the following:

(1)The permittee shall submit an application on a form designated by the city manager or his designee.(2)The permittee shall agree to restore the disturbed right-of-way to a condition equal to or better than before it was disturbed.(3)The permittee shall pay a fee in accordance with the fee current schedule adopted by the commission.(4)The permittee shall post a bond in an amount in accordance with the schedule contained herein but not less than 150 percent of the amount required to restore any foreseeable damage unless waived by the city manager.(5)The permittee shall present proof of liability insurance to the city in accordance with the schedule contained herein. (Ord. No. 2982, § 1(14-1-10), 7-3-2018)

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 5).

Full Breakdown

City code section 38-118 requires easement, license, or permit authorization before any facilities go into a Kissimmee right-of-way, and bars construction or excavation there until a permit is obtained from the city manager or designee. Getting one requires submitting an application on the city's form, agreeing to restore the disturbed right-of-way to a condition equal to or better than before, paying the current fee schedule, posting a bond of at least 150 percent of the foreseeable repair cost (waivable by the city manager), and providing proof of liability insurance. A companion section makes unpermitted installation or excavation a code violation.

Violations & Fines

Installing or excavating in the right-of-way without a permit is a code violation under section 1-22, with each day of non-compliance treated as a separate violation until it is fixed or removed.

Frequently Asked Questions

Who issues right-of-way permits in Kissimmee?
The city manager or their designee, based on a submitted application and the current fee schedule.
What happens if I skip the permit?
Unpermitted installation or excavation in the right-of-way is a code violation punishable under section 1-22, with each day counted as a separate violation.

Sources & Official References

Other rules in Kissimmee

All Kissimmee rules

Florida rules heatmap·Compare Kissimmee to another location·View the Florida sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Kissimmee, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.