Long Branch, NJ Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit authority
Director of Public Works
Permit fee
$5 plus cost of required tests
Advance notice
24 hours before pouring concrete
Exempt
Repairs under 8 linear feet
Rule
No blacktop over concrete sidewalks
Curb cuts
Full section removal required, no recapping

Summary

Before building, removing or repairing a sidewalk, driveway apron, curb or gutter in the public right-of-way in Long Branch, Monmouth County, New Jersey, property owners or their agents must get a $5 permit from the Director of Public Works and give 24 hours' notice before pouring concrete.

It shall be unlawful for any person to construct or remove or cause to be constructed or removed any sidewalk, driveway apron, curb or gutter or any part thereof within any public right-of-way in the city without first having obtained a permit to do so from the Director of Public Works. ... A fee of $5 shall be charged for each permit, and in addition thereto, the applicant shall pay the cost of all tests which the Director of Public Works deems necessary. ... The applicant shall notify the Department of Public Works at least 24 hours prior to the time of pouring or laying any sidewalk, driveway apron, curb or gutter so that the Department may arrange for adequate inspection and testing.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4904719; v48 updated 2026-06-10; through 06-10-2026).

Full Breakdown

Chapter 297, Article II covers any work touching a sidewalk, driveway apron, curb or gutter within a public right-of-way. Section 297-5 makes a permit mandatory before construction or removal, and Section 297-6 requires the application to state the applicant's name and address, the name and address of whoever will do the work, the property owner if different, the job location, the estimated cost, and a line-and-grade plan showing the work's exact position relative to a street intersection or other fixed point, its width, its relationship to street and property grade, and, for a driveway apron, its slope.

The Director of Public Works can demand any further information needed to judge code compliance. The permit fee is $5, plus the cost of any tests the Director requires, both payable when the application is filed. All materials and workmanship must follow the city's on-file specifications; removed sidewalks, aprons, curbs or gutters must be promptly replaced to those specifications, concrete sidewalks may never be covered with blacktop, and a required curb cut or driveway depression means the whole affected section of curb must be removed and replaced rather than broken and recapped.

The applicant must notify the Department of Public Works at least 24 hours before pouring or laying any sidewalk, driveway apron, curb or gutter so an inspector can be scheduled. The article exempts sidewalk work covered by a major subdivision's performance guaranties and the repair or replacement of less than eight linear feet of existing sidewalk.

Violations & Fines

A violation of this article is punishable under the general penalty provisions in Chapter 1, Article I of the City Code, enforced through the Long Branch Municipal Court. Because the permit function sits with the Director of Public Works, unpermitted work can also be stopped or ordered corrected before the City will approve the finished sidewalk, apron or curb.

Frequently Asked Questions

Do I need a permit to replace my driveway apron in Long Branch?
Yes, unless the work is less than eight linear feet of existing sidewalk. Section 297-5 requires a permit from the Director of Public Works before constructing or removing any sidewalk, driveway apron, curb or gutter within the public right-of-way.
How much does a Long Branch sidewalk or curb permit cost?
The filing fee is $5 under Section 297-7 of the City Code, plus the cost of any tests the Director of Public Works decides are necessary for the job, both of which must be paid before the application is processed and the permit issued.
Can I cover my old concrete sidewalk with blacktop instead of replacing it?
No. Section 297-8 specifically prohibits replacing or covering a concrete sidewalk with blacktop, and any curb cut or driveway depression requires removing and replacing the entire affected section of curb rather than breaking and recapping it, so partial patches are not permitted.
How much notice must I give before pouring a new sidewalk?
At least 24 hours. Section 297-9 requires notifying the Department of Public Works a full day ahead of pouring or laying any sidewalk, driveway apron, curb or gutter so an inspector can be scheduled to review and test the work.

Sources & Official References

Other rules in Long Branch

All Long Branch rules

Compare Long Branch to another location·View the New Jersey sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Long Branch, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.