Key Facts

Who maintains
Abutting property owner builds and repairs sidewalk
Permit lead time
7 days before repair or replacement work
Permit fee
No fee charged for a sidewalk permit
Noncompliance notice
20 days to repair after statutory notice
Cost if city acts
Full cost billed as a special tax

Summary

In the City of Mosinee, section 70-73 puts the duty to build, repair and perpetually maintain the sidewalk fronting a property on the abutting owner, who pays the full construction cost. Owners need a city permit before laying or repairing a public sidewalk, and if an owner ignores a 20-day repair notice, the common council fixes it and bills the cost as a special tax.

(a)Owner to construct. It shall be the duty of the abutting owner to build, repair, construct and perpetually maintain sidewalks along or upon any street, alley or highway in the city and to pay the entire cost of construction thereof. ... (b)Permit required. No person shall hereafter lay, remove, replace or repair any public sidewalk within the city unless he is under contract with the city to do such work or has obtained a permit therefor from the administrator at least seven days before work is proposed to be undertaken. ... (d)Sidewalk repair or replacement. Pursuant to Wis. Stats. § 66.615, the common council may order property owners to repair or remove and replace any sidewalk which is unsafe, defective or insufficient. If the property owner shall fail to so repair or remove and replace such sidewalk for a period of 20 days after service of the notice provided in Wis. Stats. § 66.615(3)(c), the common council shall repair or construct such sidewalk, and the administrator shall enter the total cost thereof upon the tax roll as a special tax against such lot or parcel of land.

Full Breakdown

Chapter 70, Article III of the Mosinee Code of Ordinances places sidewalk maintenance squarely on the property owner. Section 70-73(a) makes it the abutting owner's duty to build, repair, construct and perpetually maintain the sidewalk along any street, alley or highway fronting the parcel, and to pay the entire cost of construction. The common council designates where sidewalks go by resolution, and no one may remove a sidewalk without council permission. Before doing the work, section 70-73(b) requires a permit from the city administrator at least seven days ahead of starting, unless the work is done under a city contract; the city charges no fee for that permit.

Section 70-73(c) sets detailed specifications an owner's contractor must follow: air-entrained concrete of six bags per cubic yard, residential walks five feet wide and at least four inches thick (six inches through driveway aprons), commercial and industrial walks at least eight feet wide and five inches thick, expansion joints every 40 feet, and curing for 48 hours in normal weather or 96 hours below 50 degrees Fahrenheit. If the common council finds a sidewalk unsafe, defective or insufficient, section 70-73(d) lets it order the owner to repair or replace it under Wis.

615; an owner who does not comply within 20 days of the statutory notice loses the choice, because the city then does the work itself and puts the full cost on the property's tax roll as a special assessment. Curb and gutter repair follows the same cost-shifting rule under section 70-73(f), with the benefited property paying 100 percent of that cost as well.

Violations & Fines

An owner who fails to repair a sidewalk within 20 days of the city's Wis. Stats. § 66.615(3)(c) notice does not face a direct fine, but loses control of the job: the common council has the work done and the administrator enters the full cost on the property's tax roll as a special tax against the lot, collected the same as any other property tax.

Frequently Asked Questions

Who is responsible for fixing a cracked sidewalk in Mosinee?
The owner of the abutting property is. Section 70-73(a) of the Mosinee Code of Ordinances makes it the owner's duty to build, repair, construct and perpetually maintain the sidewalk along any street, alley or highway the property touches, and the owner pays the full cost of the work.
Do I need a permit to replace my own sidewalk in Mosinee?
Yes, unless the city itself has contracted for the work. Section 70-73(b) requires a permit from the city administrator at least seven days before starting, though the city does not charge a fee for issuing it. The finished sidewalk must also meet the width, thickness and jointing specifications in section 70-73(c).
What happens if I ignore the city's sidewalk repair order?
The common council can have the city do the repair and charge you for it. Under section 70-73(d), once 20 days pass after the statutory notice under Wis. Stats. § 66.615(3)(c), the city repairs or replaces the sidewalk itself and the administrator enters the total cost on the tax roll as a special tax against the property.

Sources & Official References

Other rules in Mosinee

All Mosinee rules

Compare Mosinee to another location·View the Wisconsin sidewalk & pedestrian rules overview

Get notified when Sidewalk Repair in Mosinee, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Sidewalk Repair in Nearby Cities

How other cities in Marathon County handle sidewalk repair.

Rothschild, WI
Some Restrictions
Wausau, WI
Some Restrictions