Madera, CA Solar Energy: Expedited Solar Permitting (2026)

Light Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Size limit
10 kW AC or 30 kW thermal
Same-day permit
Over-the-counter applications
Electronic permit
1-3 business days
Required inspections
One, unless it fails
Adopting ordinance
Ord. 927 C.S., 8-19-2015

Summary

Madera must issue a nondiscretionary building permit the same day for over-the-counter, or within 1-3 business days for electronic, applications for small rooftop solar systems up to 10 kW AC that meet the city's checklist.

The Community Development Director shall implement an administrative, nondiscretionary review process to expedite approval of small residential rooftop solar energy systems. The Building Division shall issue a building permit, the issuance of which is nondiscretionary, on the same day for over-the-counter applications or within 1-3 business days for electronic applications upon receipt of a complete application that meets the requirements of the approved checklist and standard plan. ... Only one inspection shall be required and performed by the Building and Safety Division for small residential rooftop solar energy systems eligible for expedited review.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2024 S-50: Current through Ordinance 1010 C.S., passed 6-5-24).

Full Breakdown

, passed August 19, 2015, implements the state Solar Rights Act and AB 2188 through an expedited permit process. 02 defines a small residential rooftop solar energy system as one no larger than 10 kilowatts AC nameplate rating or 30 kilowatts thermal, installed on a single or two-family dwelling, that conforms to adopted state and city codes and does not exceed the city's maximum legal building height. 06, the Community Development Director must run an administrative, nondiscretionary review, and the Building Division issues the permit the same day for over-the-counter applications, or within one to three business days for electronic applications, once a complete application meeting the approved checklist and standard plan is received.

The Chief Building Official's review is limited to whether the application meets local, state and federal health and safety requirements; only if the official finds substantial evidence of a specific, adverse impact on public health and safety may the applicant instead be required to obtain an Administrative Use Permit, appealable to the Planning Commission. 05 requires the city to make all application documents available on its website and to accept electronic submittal by email or internet, with the standard plan and checklist conforming to the California Solar Permitting Guidebook. 06(G), though a follow-up inspection is authorized if the system fails.

Violations & Fines

A permit for a qualifying small rooftop solar system cannot be delayed or denied outright once the application is complete and meets the checklist; the only additional step allowed is a required Administrative Use Permit, and only where the Chief Building Official documents substantial evidence of a specific, adverse health or safety impact, a decision the applicant can appeal to the city Planning Commission under § 9-4.06.

Frequently Asked Questions

How fast can I get a solar permit in Madera?
Under § 9-4.06, the Building Division issues the permit the same day for over-the-counter applications or within one to three business days for electronic applications, once the application meets the approved checklist and standard plan.
Can Madera deny my expedited solar permit?
Only if the Chief Building Official finds substantial evidence the system could have a specific, adverse impact on public health or safety, in which case an Administrative Use Permit can be required, and that decision is appealable to the Planning Commission.
How many inspections does a small rooftop system need?
Section 9-4.06(G) requires only one inspection for systems eligible for expedited review, though subsection (I) authorizes a follow-up inspection if the system fails the first one.

Sources & Official References

Other rules in Madera

All Madera rules

California rules heatmap·Compare Madera to another location·View the California solar energy overview

Get notified when Expedited Solar Permitting in Madera, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.