Medford, OR Solar Energy: Expedited Solar Permitting (2026)

Few Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Medford Code § 10.200(3)(b)(v)
Exempt use
Solar Photovoltaic/Solarvoltaic systems, per ORS 757.360
Review skipped
Site Plan and Architectural Review (SPAR/SPAC)
Historic exception
Landmarks Commission reviews landmark/district installs
Other standards
Access, parking, landscaping rules still apply

Summary

Medford Code § 10.200(3)(b)(v) exempts solar photovoltaic energy systems from Site Plan and Architectural Review, the discretionary land-use review normally required for commercial, industrial and multi-family development. That skips straight to a building permit, unless the panels sit on a historic landmark or within a historic district, where the Landmarks and Historic Preservation Commission takes over review instead.

(3) Exemptions From the Site Plan and Architectural Review, SPAR – Type II and SPAC – Type III, Requirement. (a) An exemption from Site Plan and Architectural Commission review does not exempt the use or development from compliance with the applicable standards of this chapter... (b) The following uses or developments do not require Site Plan and Architectural Commission review: ... (v) Solar Photovoltaic/Solarvoltaic energy systems, as defined in ORS 757.360, except when located on historic landmarks or within historic districts, in which case the review authority shall be the Landmarks and Historic Preservation Commission.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2026-32, passed May 6, 2026).

Full Breakdown

200 establishes Site Plan and Architectural Review (SPAR-Type II or SPAC-Type III) to check the functional and aesthetic adequacy of commercial, industrial, Cottage Cluster, and multi-family development before a building permit can issue. 360,' as exempt, removing the months-long Type II or Type III land-use process that other commercial construction faces. The only carve-out is for solar installations on historic landmarks or within historic districts, where the Landmarks and Historic Preservation Commission becomes the review authority instead of the Site Plan and Architectural Commission. 200(3)(a), it does not excuse a solar project from other applicable standards, such as access, parking, riparian protection, or landscaping, and it does not apply if the property is otherwise subject to a conditional use permit or park development review.

200(4) through (8) otherwise impose on commercial and multi-family development. The exemption was carried into the code's Site Plan and Architectural Review chapter alongside other by-right uses, including small building additions and detached single-family construction, reflecting the City's approach of removing discretionary review for improvements that pose limited land-use compatibility concerns.

Violations & Fines

Installing solar photovoltaic panels on a historic landmark or within a historic district without first obtaining Landmarks and Historic Preservation Commission review is a Section 10.200(3)(b)(v) violation, since the SPAC/SPAR exemption does not apply there. A solar installation that also triggers another required review, such as a conditional use permit or park development review, cannot rely on this exemption to skip that separate process.

Frequently Asked Questions

Does installing solar panels in Medford require Site Plan and Architectural Review?
No. Section 10.200(3)(b)(v) exempts Solar Photovoltaic/Solarvoltaic energy systems, as defined in ORS 757.360, from Site Plan and Architectural Review, so a project moves straight to the building permit stage instead of the Type II or Type III land-use process.
Is there an exception to Medford's solar permit exemption?
Yes. If the panels are located on a historic landmark or within a historic district, Section 10.200(3)(b)(v) makes the Landmarks and Historic Preservation Commission the review authority instead, so the general SPAC/SPAR exemption does not apply there.
Does the solar exemption excuse a project from other Medford development standards?
No. Subsection (3)(a) makes clear an exemption from Site Plan and Architectural Commission review does not excuse compliance with other applicable standards such as access, parking, riparian protection and landscaping, and does not apply to uses already subject to a conditional use permit or park development review.

Sources & Official References

Other rules in Medford

All Medford rules

Compare Medford to another location·View the Oregon solar energy overview

Get notified when Expedited Solar Permitting in Medford, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.