Key Facts

Permit
required from Zoning Administrator before construction
Attached panel projection
2 ft front/side, 6 ft rear yard
Freestanding panel
rear yard only, max 6 ft, 5 ft off rear line
Application
scaled plot plan required (§5.25.3)
Fee
set by Master Fee Schedule, paid before permit
Grandfathered panels
installed before Sept 18, 1985 may continue

Summary

Installing solar panels anywhere in Blue Hill's residential zoning jurisdiction requires a permit from the Zoning Administrator before construction begins. Section 5.25 sets specific setback allowances for panels attached to the house, caps freestanding rear-yard panels at six feet, and requires a scaled plot plan and a permit fee under the Master Fee Schedule before the building permit issues.

5.25 Solar Panels No solar panel shall be constructed within the residential zoning jurisdiction of the City of Blue Hill unless a permit therefor is approved and issued by the Zoning Administrator and is constructed in conformance with the following requirements. ... 5.25.1 Solar panels shall conform to the required front, side and rear lot setback requirements except as provided herein: a. A solar panel which is attached to an integral part of the principal building may project two feet (2’) into the front yard; six feet (6’) into the rear yard; and two feet (2’) into the side yard. ... 5.25.3 The application for a permit shall be accompanied by a plot plan drawn to scale showing property lines, existing structures on the lot, proposed solar panel location with respect to property lines, and dimensions of the proposed solar panel. 5.25.4 A permit fee is required. This permit fee shall be paid prior to the issuance of the building permit. The amount of the fee shall be as established in the Master Fee Schedule.

Full Breakdown

25, Solar Panels, of the City of Blue Hill Official Zoning Ordinance (Ordinance No. 699, adopted May 8, 2018) states that no solar panel may be built within the residential zoning jurisdiction of the City of Blue Hill unless the Zoning Administrator has approved and issued a permit, and any electrical, plumbing, or heating work that comes with the installation needs its own separate permits. 1 grants two specific exceptions. A panel attached to the principal building may project two feet into the front yard, six feet into the rear yard, and two feet into the side yard.

A freestanding panel may only sit in the required rear yard, capped at six feet in height, set back at least five feet from the rear lot line and at least one foot from any existing easement, and it may never be placed in a required side or front yard. 2 requires the physical structure and its connections to conform to the applicable building codes. 3 requires a plot plan drawn to scale showing property lines, existing structures, the proposed panel location, and its dimensions.

4 requires a permit fee, set by the Master Fee Schedule, paid before the building permit is issued. 5 lets a solar panel erected before September 18, 1985 under a valid building permit keep operating even if it no longer meets these standards, so long as it stays in operational condition.

Violations & Fines

Building or maintaining a solar panel without the required Zoning Administrator permit, or outside the section 5.25.1 setback and height limits, is a Zoning Ordinance violation. Under section 9.8 that carries a misdemeanor fine of up to $100 per offense, with each day the panel remains out of compliance treated as its own separate offense.

Frequently Asked Questions

Do I need a permit to install solar panels in Blue Hill?
Yes. Section 5.25 requires a permit approved and issued by the Zoning Administrator before construction, and any electrical, plumbing, or heating work included in the installation needs its own separate permits.
How close to my property line can a freestanding solar panel go?
It must sit in the required rear yard only, be no taller than six feet, stay at least five feet from the rear lot line, and stay at least one foot from any existing easement, per section 5.25.1.b.
Is there a fee for the solar permit?
Yes. Section 5.25.4 requires a permit fee set by the city's Master Fee Schedule, and it must be paid before the building permit is issued.
What if my solar panel predates the ordinance?
Section 5.25.5 lets a solar panel erected before September 18, 1985 under a valid building permit keep operating even if it does not meet the current standards, as long as it stays in operational condition.

Sources & Official References

Other rules in Blue Hill

All Blue Hill rules

Compare Blue Hill to another location·View the Nebraska solar energy overview

Get notified when Panel Permits in Blue Hill, NE changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.