Key Facts

Flat permit fee
$65.00 per system
Governing section
Lawrence City Code § 5-254(c)
Condition
Applies only with no structural change
Structural roof work
Needs full § 5-254(a) fee schedule
Rough inspection
Required before concealing wiring

Summary

The City of Lawrence charges a flat $65.00 permit fee for solar, thermal and photovoltaic systems that require no structural change to the building, under Lawrence City Code § 5-254(c). The installation still needs the permit application described in §§ 5-220 and 5-227 before work starts, reviewed by the building safety division of Planning and Development Services.

On buildings, structures, electrical, gas, mechanical, and plumbing systems or alterations requiring a permit, a fee for each permit shall be paid as required, in accordance with the schedule as established by the applicable governing authority. ... (c)Other inspections and fees. ... Permits for solar, thermal, and photovoltaic systems (requiring no structural change to the building) $65.00

Full Breakdown

00 fee for permits covering solar, thermal and photovoltaic systems that require no structural change to the building, distinct from the sliding valuation-based schedule that applies to most other construction work in § 5-254(a) and separate from the flat per-dwelling fee schedule for new one- and two-family homes in § 5-254(b). Getting to that fee starts with the general permit rule in § 5-220, which requires anyone installing, altering or replacing equipment regulated by chapter 5 to first apply to the building official; the application under § 5-227 must describe the work, locate the property, state the intended use, include construction documents, and state the estimated valuation of the installation.

00 rate, and can require a registered design professional's documents where special conditions exist. Once permitted, the rough electrical inspection required under § 5-306 covers the wiring tying panels or inverters into the building's electrical system, before it is concealed and before any framing inspection on the same job. 00 rate itself.

Violations & Fines

Installing a solar, thermal or photovoltaic system before the permit issues adds a fee equal to the base permit charge under § 5-256, even though the base fee itself is only $65.00 for a non-structural installation. If the building official finds the installation actually required a structural change that was not disclosed, the permit can be treated as issued on inaccurate information and suspended under § 5-232.

Frequently Asked Questions

How much is a solar panel permit in Lawrence?
A flat $65.00 for a solar, thermal or photovoltaic system that requires no structural change to the building, under Lawrence City Code § 5-254(c). That is separate from the sliding, valuation-based fee schedule that applies to most other construction work in § 5-254(a).
What if my solar installation needs new roof framing?
Then it is no longer a no-structural-change installation, and the building official can require the standard valuation-based permit fee and construction documents under §§ 5-235 and 5-254(a) instead of the flat $65.00 rate, along with a registered design professional's plans where conditions warrant it.
Does a solar permit still need an inspection?
Yes. The rough inspection required under § 5-306 covers the electrical connections tying the panels or inverter into the building's wiring before that wiring is concealed, and it has to happen before any framing inspection on the same job.

Sources & Official References

Other rules in Lawrence

All Lawrence rules

Compare Lawrence to another location·View the Kansas solar energy overview

Get notified when Panel Permits in Lawrence, KS changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.