Key Facts
- Building subcode PV permit fee
- $100 flat
- Electrical subcode fee, 1-50 kW
- $125
- Electrical subcode fee, 51-100 kW
- $150
- Electrical subcode fee, over 100 kW
- $675
- Fire protection subcode PV fee
- $100 flat
Summary
Ridgewood requires two construction subcode permits for a photovoltaic installation: a $100 building subcode permit plus an electrical subcode permit priced by system size, from $125 for systems up to 50 kilowatts to $675 for systems over 100 kilowatts.
Building subcode fees. The building subcode fees shall be as follows: ... 18. Photovoltaic systems: $100. ... For photovoltaic systems, the fee shall be based on the design kilowatt rating of the solar voltaic system as follows: (a) For one to 50 kilowatts, the fee shall be $125. (b) For 51 to 100 kilowatts, the fee shall be $150. (c) For greater than 100 kilowatts, the fee shall be $675.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4854397; v35 updated 2026-04-22; through 04-22-2026).
Full Breakdown
The Village's consolidated fee schedule, Village of Ridgewood Code § 145-6, prices solar photovoltaic installations under two separate Uniform Construction Code subcodes. The building subcode fee list charges a flat $100 for photovoltaic systems, the same flat rate applied to permit updates and to smaller accessory items like garden sheds. The electrical subcode fee list prices the same installation by its design kilowatt rating: $125 for systems from one to 50 kilowatts, $150 for systems from 51 to 100 kilowatts, and $675 for anything larger than 100 kilowatts.
A separate fire protection subcode line item also lists a $100 photovoltaic charge, reflecting that a rooftop or ground-mounted array can trigger review by more than one subcode official under the enforcing agency structure set out in § 125-1(A), the Building Subcode Official, Electrical Subcode Official, and Fire Protection Subcode Official each administering their own piece of the installation. Because § 125-3(A) requires all subcode permit fees to be paid before the Department of Building and Inspections issues the permit, an installer or homeowner effectively pays the flat building subcode fee, the kilowatt-tiered electrical subcode fee, and, where fire subcode review applies, the fire protection fee, all before racking and panels can go up.
Anyone applying should have the system's design kilowatt rating documented up front, since that figure determines which electrical subcode tier applies and therefore the largest component of the total permit cost.
Violations & Fines
Installing a photovoltaic system without the required building and electrical subcode permits exposes the owner or installer to enforcement by the Department of Building and Inspections, including stop-work action and after-the-fact assessment of the applicable flat and kilowatt-tiered permit fees before the system can be connected or approved.
Frequently Asked Questions
How much does a solar panel permit cost in Ridgewood?
Is the solar permit fee based on panel count or system size?
Does a solar installation need more than one permit?
Sources & Official References
Other rules in Ridgewood
Compare Ridgewood to another location·View the New Jersey solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.