Key Facts

1-50 kW fee
$150
51-100 kW fee
$300
Over 100 kW
Add $300 per additional 100 kW
Microinverter fee
Flat $75 regardless of count
Minimum electrical fee
$65 per § 252-6C(6)

Summary

Installing solar panels in Toms River Township requires an Electrical Subcode permit, and the fee is tiered by system size under § 252-6C(2)(q) of the Township Code: $150 for systems up to 50 kilowatts, $300 for 51 to 100 kilowatts, and an added $300 for every additional 100 kilowatts beyond that. Separate fees apply to the inverters and disconnect equipment that pair with the panels.

Solar devices. For photovoltaic systems, the fee shall be based on the designated kilowatt rating of the solar photovoltaic system, as follows: One kilowatt to 50 kilowatts: $150. Fifty-one kilowatts to 100 kilowatts: $300. Greater than 100 kilowatts: For each additional 100 kilowatts add $300.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4954830; v33 updated 2026-04-22; through 04-22-2026).

Full Breakdown

Toms River Township regulates solar photovoltaic installations as part of the Electrical Subcode fee schedule in Chapter 252, Construction Codes, Uniform, rather than through a stand-alone solar ordinance. Section 252-6C(2)(q) sets the permit fee for solar devices based on the designated kilowatt rating of the photovoltaic system: systems rated from one to 50 kilowatts pay $150, systems from 51 to 100 kilowatts pay $300, and systems over 100 kilowatts pay an additional $300 for each additional 100 kilowatts. The same fee schedule reaches the equipment that pairs with rooftop or ground-mounted solar arrays.

Under § 252-6C(2)(r), inverter fees other than microinverters run $25 for one to 10 kilowatts, $65 for 11 to 45 kilowatts, and an added $25 for every additional 10 kilowatts above 45; § 252-6C(2)(s) sets a flat $75 fee for microinverters, defined as inverters rated under one kilowatt, regardless of how many are installed. Disconnects and combiner panels are billed separately under § 252-6C(2)(t) by amperage, from $75 for up to 100 amperes to $650 for 601 to 1,000 amperes, with $75 added for each additional 100 amperes above that.

All of this work is administered by the township's Office of Construction Permits and Inspections, established under § 252-2, and the minimum Electrical Subcode fee for any permit, solar included, is $65 under § 252-6C(6).

Violations & Fines

Chapter 252 does not list a separate solar-specific penalty; installing a photovoltaic system, inverter, or disconnect without the required Electrical Subcode permit and fee under § 252-6C is treated as a general Uniform Construction Code violation, enforced by the Office of Construction Permits and Inspections and backstopped by the requirement that no certificate of occupancy can issue until all required inspections and fees, including reinstatement fees for a lapsed permit, are satisfied.

Frequently Asked Questions

How much is a solar panel permit in Toms River?
It depends on system size under § 252-6C(2)(q): $150 for a photovoltaic system rated one to 50 kilowatts, $300 for 51 to 100 kilowatts, and an additional $300 for every 100 kilowatts beyond that. A typical residential rooftop array usually falls in the $150 tier.
Are there separate fees for solar inverters in Toms River?
Yes. Section 252-6C(2)(r) charges $25 for inverters from one to 10 kilowatts and $65 for 11 to 45 kilowatts, with $25 added per additional 10 kilowatts above that, while § 252-6C(2)(s) sets a flat $75 fee for microinverters no matter how many are installed.
Who reviews solar permit applications in Toms River Township?
The Office of Construction Permits and Inspections, the enforcing agency established under § 252-2 of the Township Code, administers Electrical Subcode permits, including the solar device fees in § 252-6C(2)(q), and the minimum fee for any electrical permit is $65.

Sources & Official References

Other rules in Toms River

All Toms River rules

Compare Toms River to another location·View the New Jersey solar energy overview

Get notified when Panel Permits in Toms River, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Panel Permits in Nearby Cities

How other cities in this county handle panel permits.

Brick, NJ
Some Restrictions