Caddo Parish, LA Trash & Recycling: Dumpster Rules (2026)
Key Facts
- Enclosure height
- 6 ft minimum, 8 ft maximum
- Enclosure design
- Solid 3 sides, solid gate
- Placement ban
- Front/corner side yard, right-of-way
- Enclosure permit
- Building permit required
- Alley containers
- Exempt from enclosure rule
- Grandfathering
- Ends at redevelopment/expansion
Summary
Commercial dumpsters and recycling containers in unincorporated Caddo Parish cannot sit in a front or corner side yard or on the right-of-way, and the Unified Development Code requires a solid, gated enclosure six to eight feet tall around three sides, built under its own building permit.
1.Dumpsters and recycling containers are prohibited in the front or corner side yard. No dumpsters or recycling containers may be located on any public right-of-way.2.All dumpsters and recycling containers must be fully enclosed on three sides by a solid fence, wall, or wall extension of the principal building a minimum of six feet and a maximum of eight feet in height. The enclosure must be gated. Such gate must be solid. Such construction requires a building permit. This requirement does not apply to refuse containers located in an alley.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 26 | Unified Development Code: Supplement 2).
Full Breakdown
UDC § 7.3.T governs dumpster and container placement for every property in unincorporated Caddo Parish, not just single-family lots. Two placement bans apply first: dumpsters and recycling containers cannot go in the front or corner side yard, and none may be located on any public right-of-way (§ 7.3.T.1). Where a dumpster is used, it has to be screened by an enclosure that is fully solid on three sides, built as a fence, wall, or extension of the building's own wall, standing a minimum of six feet and a maximum of eight feet tall; the enclosure needs a gate, and the gate itself must be solid rather than open lattice or chain-link (§ 7.3.T.2).
That enclosure counts as construction requiring its own building permit before it goes up. The one carve-out is for refuse containers set in an alley, which do not need the three-sided enclosure at all (§ 7.3.T.2). Drainage matters too: a dumpster cannot be positioned so its disposal area drains toward a storm drain or off the site, and it has to stay covered rather than left open to drain freely onto the pavement (§ 7.3.T.3). Properties that already existed when the Code took effect, and whose dumpsters were not previously required to be enclosed, are exempt from the enclosure rule unless the site is later redeveloped or the existing building or parking lot expands (§ 7.3.T.5).
Violations & Fines
The Zoning Administrator enforces the dumpster standards and can order an unscreened or misplaced container brought into compliance, seeking an injunction through the Parish Attorney if necessary (UDC § 19.1-19.2). Building without the required enclosure permit, or ignoring a compliance order, is fined under UDC § 19.3-19.4, with each day of noncompliance treated as a separate offense.
Frequently Asked Questions
Does my commercial dumpster in Caddo Parish need to be screened?
Can I put a roll-off dumpster in my parking lot facing the street?
My building is older and never had a dumpster enclosure. Do I have to build one now?
Sources & Official References
Other rules in Caddo Parish
Compare Caddo Parish to another location·View the Louisiana trash & recycling overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.