Key Facts
- Connection trigger
- Reuse main within 500 feet of new development
- Extension cost
- Developer pays full cost to extend main
- Fee in lieu
- 50% of extension cost if main is farther
- Large user threshold
- 75,000 gallons/day average demand
- Rate schedule
- Schedule 1-R, set annually through 2028
- Post-2028 rates
- 2.5% automatic yearly escalator from Oct. 2029
- Non-compliance
- City may compel connection by lawful action
Summary
New residential, commercial and industrial development in Winter Haven's utility service area must connect to the city's reclaimed/reuse water system whenever a reuse main sits within 500 feet, under Code of Ordinances § 19-36(b). Developers pay to extend that main into the project, or, if the nearest reuse main is farther than 500 feet, cover half the extension cost as a fee in lieu of construction.
(b)All new development including, but not limited, to residential, commercial, and industrial developments located within the City of Winter Haven utility service area shall be required to connect to and utilize the reclaimed/reuse water system if a reclaimed/reuse water main is located within five hundred (500) feet of the proposed development. The owner/developer shall be liable for payment of the cost to extend the reclaimed/reuse main and reclaimed/reuse water distribution system within the new development. For all such new developments located within the City of Winter Haven utility service area, but more than five hundred (500) feet from a reclaimed/reuse water main, a fee in lieu of installation of the required extension of the reclaimed/reuse water main and reclaimed/reuse water distribution system within the new development shall be paid in an amount equal to fifty (50) percent of the total cost as determined by the designing engineer of record and as approved by the city engineer.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 108).
Full Breakdown
Section 19-36, in Article II's Division 1 on water service generally, requires new development inside the City of Winter Haven utility service area to connect to and use the reclaimed/reuse water system for irrigation once a reclaimed/reuse main is within five hundred feet of the project, with the owner or developer liable for the cost of extending that main and its distribution piping into the new development. Where the closest reuse main is farther than five hundred feet away, the owner or developer instead pays a fee in lieu of construction equal to fifty percent of the extension's total cost, as determined by the project's design engineer and approved by the city engineer, and design standards for the extension come from the city engineer's office.
Reuse service is billed and classified separately from potable water under § 19-138(d)(8): a 'general service' reuse connection covers ordinary properties, while a 'large user' connection is any customer with a potential average daily demand of 75,000 gallons per day of reuse water or more and must sign a large user agreement with the city, in pressure, non-pressure, or interruptible/disposal form, approved by the utility director and city commission. 5 percent yearly escalator absent a new commission schedule.
Violations & Fines
Section 19-36(d) backs this chapter's connection mandates: if a required connection is not made within the applicable time limit, the city water department 'shall proceed by lawful action to compel the owner to make the required connection.' A connected customer who misses a reuse water bill faces the same collections path as potable water under § 19-6: a cut-off notice after 30 days past due, seven more days to pay, then disconnection until the overdue bill, delinquent fee, and updated deposit are paid.
Frequently Asked Questions
Does Winter Haven require new construction to connect to reuse water?
What if the nearest reuse main is more than 500 feet from my project?
How does Winter Haven classify large reuse water customers?
What happens if I don't connect to city water or reuse water when required?
Sources & Official References
Other rules in Winter Haven
Florida rules heatmap·Compare Winter Haven to another location·View the Florida water use rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.