- Governing guidelines
- Stonecrest Overlay District Design Guidelines, dated May 2008
- Administered by
- City planning director or designee
- Review deadline
- 30 days from complete application
- Appeal path
- Zoning Board of Appeals, Sec. 7.5.2
- Exempt work
- Interior repairs not changing exterior/footprint
- Covers
- Overlay Tiers IV-VI near Mall at Stonecrest
Summary
In the City of Stonecrest, new buildings and major renovations inside the Stonecrest Area Overlay District, the mixed-use tiers built around the Mall at Stonecrest, must follow the Stonecrest Overlay District Design Guidelines dated May 2008. Zoning Ordinance Sec. 3.5.18 lets the planning director create, administer and amend these architectural, landscaping, signage, fencing, lighting and street furniture standards, and every project needs the director's certificate of compliance before permits issue.
The Stonecrest Overlay District Design Guidelines dated May 2008 in DeKalb County, shall apply to all uses and structures within the Stonecrest Overlay District and shall be maintained by the planning director and available for public inspection. The design guidelines provide acceptable minimum standards to guide design and development within this overlay district. The planning director or designee is authorized to create, administer, and amend design guidelines for the Stonecrest Area Overlay District. These guidelines provide acceptable architectural design controls, landscaping, detail drawings, signage, fencing, lighting, street and site furniture, and grating criteria. These guidelines shall be used to promote proper design criteria and shall guide the planning director or designee in deciding whether a proposed design complies with the requirements of the Stonecrest Area Overlay District.
Full Breakdown
The Stonecrest Area Overlay District covers the tiered mixed-use zones the city inherited from DeKalb County at incorporation, including the Transitional Mixed-Use Zone (Tier IV), the Cluster Village Mixed-Use Zone (Tier V) and the Viewshed Zone (Tier VI) that ring the Mall at Stonecrest and the Arabia Mountain area. Sec. 3.5.18 makes the Stonecrest Overlay District Design Guidelines, dated May 2008, binding on every use and structure in the district and puts the planning director in charge of keeping the guidelines on file for public inspection and amending them as needed.
The guidelines set the architectural design controls, landscaping, detail drawings, signage, fencing, lighting, street and site furniture and grading criteria the director applies when deciding whether a proposed design fits the overlay. Sec. 3.5.19 backs this up procedurally: before any land disturbance, building or sign permit is issued in the district, the applicant must first submit a conceptual plan package to the director, pay a council-set fee, and receive a certificate of compliance signed by the director or a designee. The director has 30 days from a complete application to decide, and if the plans do not comply, the director must notify the applicant in writing of exactly how they fall short.
Sec. 3.5.20 spells out what the conceptual plan package must contain, down to a site location map, floodplain and wetlands delineation, building heights and setbacks, and standard details for signs, sidewalks, streetlights, fencing and street furniture demonstrating compliance with the design guidelines. Minor work is not swept in: permits for repairs, interior alterations, or tenant buildout that do not change a building's exterior appearance or footprint are exempt from the overlay's design requirements. Any appeal of the director's compliance decision goes to the zoning board of appeals under Sec. 7.5.2.
Violations & Fines
A design that the director finds noncompliant is refused a certificate of compliance under Sec. 3.5.19.C, which blocks the land disturbance, building and sign permits the project needs; the director must state in writing how the plans fail to meet the guidelines, and the applicant can appeal that call to the zoning board of appeals under Sec. 7.5.2. Beyond the permit block, unpermitted work in the city is punishable under the Code's general penalty, Sec. 1-11: a fine up to $1,000.00, up to 120 days in jail, or both, with each day of a continuing violation a separate offense.
Frequently Asked Questions
Does every remodel inside the overlay need design review?
Who decides if my design meets the guidelines?
Can I appeal if the director rejects my plans?
What does the conceptual plan package have to show?
Sources & Official References
Other rules in Stonecrest
Compare Stonecrest to another location·View the Georgia zoning overlays & bonuses overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.