ADU rules in Pomona, CA, also called accessory dwelling unit regulations or granny flat ordinances, cover setbacks, owner-occupancy, parking, and permit requirements.

Key Facts

Approval timeline
60 days, ministerial, no hearing
Max size (lot <7,200 sf)
850-1,000 sq ft by bedrooms
Max size (lot ≥7,200 sf)
1,200 square feet
Height (detached)
16 ft, up to 20 ft near transit
Parking
Not required for any ADU
Impact fees
Waived for ADUs ≤749 sq ft

Summary

Pomona regulates ADUs and JADUs under Sec. 830.A of the Zoning and Development Code, approving compliant units ministerially within 60 days without a hearing. Detached ADUs on lots under 7,200 square feet cap at 850 to 1,000 square feet depending on bedroom count, height tops out at 16 feet for most detached units, and no off-street parking is required for any ADU.

Accessory Dwelling Unit. An attached or a detached residential dwelling unit that provides complete independent living facilities (permanent provisions for living, sleeping, eating, cooking, and sanitation) for one or more persons and is located on a lot with a proposed or existing primary residence. ... The City must approve or deny an application to create an ADU or JADU within 60 days from the date that the City receives a completed application. If the City does not approve or deny the completed application within 60 days, the application is deemed approved ... Lots less than 7,200 Square Feet in Area The maximum size of a detached or attached ADU may not exceed 850 square feet for a studio or one bedroom unit or 1,000 square feet for a unit with two or more bedrooms. ... a detached ADU created on a lot with an existing or proposed single family or multifamily dwelling unit may not exceed 16 feet in height. ... No parking is required for any ADU.

Source: Pomona City CodeView official code

Full Breakdown

Sec. A implements California's ADU statutes (Government Code Sec. 22) locally. A conforming ADU or JADU cannot be deemed inconsistent with the General Plan or zoning designation, cannot be counted against allowable density, and is not subject to growth-control ordinances. Two ministerial approval tracks exist. Type 1, Building-Permit-Only, covers an Interior ADU plus a JADU built within an existing or proposed single-unit dwelling or accessory structure, and a Limited Detached ADU up to 800 square feet with at least 4-foot side and rear setbacks; these need only a building permit, no discretionary review.

Type 2, Building-Permit-Only, covers everything else and applies the Specific ADU Requirements of Sec. 6: a detached or attached ADU on a lot under 7,200 square feet is capped at 850 square feet for a studio or one-bedroom unit or 1,000 square feet for two or more bedrooms, while a lot of 7,200 square feet or more allows up to 1,200 square feet. No application may be shrunk below 800 square feet by front-yard, lot-coverage, or open-space rules. Height is capped at 16 feet for a detached ADU on a single- or multi-family lot, 18 feet within a half-mile of a major transit stop, 20 feet if needed to match the primary dwelling's roof pitch, and 25 feet, or the underlying zone's limit if lower, for an attached ADU, which can never exceed two stories.

The City must approve or deny a completed application within 60 days or it is deemed approved. No off-street parking is required for any ADU, and impact fees are waived entirely for ADUs of 749 square feet or less.

Violations & Fines

An ADU or JADU built without the required building permit, or one that exceeds the applicable size or height caps in Sec. 830.A.6, is subject to City building and zoning code enforcement, including stop-work orders and correction requirements. Because ADUs still must meet all local building code requirements under Sec. 830.A.5.i, unpermitted construction can also trigger a building-code violation independent of the zoning standards.

Frequently Asked Questions

How long does Pomona take to approve an ADU?
The City must approve or deny a completed ADU or JADU application within 60 days under Sec. 830.A.4.c. If it misses that deadline, the application is automatically deemed approved unless the applicant requested a delay or the ADU application was bundled with a new primary-dwelling permit.
How big can an ADU be in Pomona?
On a lot under 7,200 square feet, a detached or attached ADU is capped at 850 square feet for a studio or one bedroom, or 1,000 square feet for two or more bedrooms, under Sec. 830.A.6.b. Lots of 7,200 square feet or larger allow up to 1,200 square feet, and no application of lot-coverage or setback rules can shrink an ADU below 800 square feet.
Do I need extra parking for an ADU in Pomona?
No. Sec. 830.A.6.f states that no parking is required for any ADU, and if a garage, carport, or covered parking space is demolished or converted to build the ADU, the City does not require those parking spaces to be replaced.

Sources & Official References

Other rules in Pomona

All Pomona rules

How Pomona compares: Easiest Cities to Build an ADU·California rules heatmap·Compare Pomona to another location·View the California accessory structures overview

Get notified when ADU Rules in Pomona, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

ADU Rules in Nearby Cities

How other cities in Los Angeles County handle adu rules.

El Monte, CA
Some Restrictions
Carson, CA
Some Restrictions
South Gate, CA
Some Restrictions
Santa Clarita, CA
Some Restrictions
Pasadena, CA
Some Restrictions
Lancaster, CA
Some Restrictions
Palmdale, CA
Some Restrictions
Lakewood, CA
Some Restrictions