Shed permit rules in Washington County, MN, also referred to as storage shed, backyard shed, or accessory building regulations, set size limits, setbacks, and when a building permit is required.

Key Facts

Permit
Building permit required for nearly all accessory structures
Under 1 acre (overlay)
720 sq ft cap
5.01-20 acres (overlay)
2,500 sq ft cap
Over 20.01 acres (overlay)
Unlimited if agricultural
Bonus shed allowance
One 120 sq ft shed exempt from count
Size table applies
Shoreland & St. Croix Overlay Districts only

Summary

Washington County requires a building permit for nearly every accessory building, and caps shed size by lot acreage inside its Shoreland and St. Croix River Overlay Districts. A parcel under 1 acre is capped at 720 square feet of accessory structures; the limit rises with acreage to unlimited square footage past 20 acres for agricultural buildings.

These county ordinances apply to unincorporated areas of Washington County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

1.2 Accessory Structures (1) Required Permits. A building permit is required for all accessory structures except agricultural buildings on a farm as defined in Minnesota Statute 16B.61. A Certificate of Compliance is required for all agricultural buildings and accessory structures in the Shoreland Management Overlay District and the St. Croix River Management Overlay District. ... (3) The following standards apply within the Shoreland Management Overlay District and the St. Croix River Management Overlay District: ... (B) The permitted sizes of accessory structures are as follows: Parcels less than 1 acre 720 sq. ft.; 1 acre – 2.49 acres 1,000 sq. ft.; 2.5 – 5 acres 2,000 sq. ft.; 5.01 acres – 20 acres 2,500 sq. ft.; 20.01+ acres *unlimited (*provided they are agricultural structures).

Full Breakdown

61, and requires a Certificate of Compliance for agricultural buildings and accessory structures located in the Shoreland Management Overlay District or the St. Croix River Management Overlay District. 01 acres carry no size limit provided the structures are agricultural. 5 and 20 acres, plus an added allowance for one shed of 120 square feet or less regardless of that count limit. 2(2)(C) unless the local unit of government approves the location and all setbacks are met. 2(1) permit requirement still applies, but the acreage-based size table does not.

Violations & Fines

Building or expanding an accessory structure without the required permit, or exceeding the overlay district's size table, is a Development Code violation. Chapter One Section 15.1 makes any violation a misdemeanor carrying a fine, imprisonment, or both, plus the cost of prosecution, and the Zoning Administrator can withhold the Certificate of Compliance needed to legalize the structure.

Frequently Asked Questions

Do I need a permit for a small storage shed?
Yes, in almost every case. Section 1.2(1) requires a building permit for all accessory structures except agricultural buildings on a qualifying farm; parcels inside the two overlay districts also need a separate Certificate of Compliance before construction.
How big can my shed be on a 3-acre lot?
If the parcel sits within the Shoreland or St. Croix River Overlay District, Section 1.2(3)(B) caps combined accessory structure area at 2,000 square feet for lots between 2.5 and 5 acres. Outside those overlay districts, this acreage table does not apply.
Does the size table apply everywhere in the county?
No. Section 1.2(3) states the acreage-based size limits apply only within the Shoreland Management Overlay District and the St. Croix River Management Overlay District; the underlying permit requirement in Section 1.2(1) applies countywide.
Can I build a shed before my house?
Generally no. Section 1.2(2)(A) bars building an accessory structure before the principal structure unless the property is a rural farm of forty acres or more, in which case the shed or barn may go up first.

Sources & Official References

Other rules in Washington County

All Washington County rules

How Washington County compares: Shed Permit Requirements by City·Compare Washington County to another location·View the Minnesota accessory structures overview

Get notified when Shed & Carport Rules in Washington County, MN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.