Key Facts

Exemption threshold
100 sq ft or less (no sanitary work)
Governing sections
Chapter 255 and § 360-62C
Codes adopted
2006 IBC and 2006 IRC (§ 255-1)
Penalty
$1 to $1,000 per day of violation
Setbacks
Still required even when permit is exempt

Summary

Unincorporated Allegany County requires a building permit for most new construction under Chapter 255, but County Code § 360-62C exempts additions or new buildings of 100 square feet or less, unless the work adds sanitary facilities or touches a septic area or well. Setbacks still apply regardless of the exemption.

These county ordinances apply to unincorporated areas of Allegany County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

No building permit is needed when new construction or enlargement of a building does not exceed 100 square feet, unless the construction involves sanitary facilities or impacts a septic area or well. However, all setbacks must be met for the particular use.

Full Breakdown

Chapter 255 of the Code of Allegany County adopts the 2006 International Building Code and the 2006 International Residential Code by reference as the county's 2007 Building Code, so any construction covered by those codes in unincorporated Allegany County needs a permit before work starts. Section 360-59 defines the permit itself as running through application, plan review, approval, inspection, and issuance of a certificate of occupancy. The county carves out one narrow exemption in § 360-62C: "No building permit is needed when new construction or enlargement of a building does not exceed 100 square feet, unless the construction involves sanitary facilities or impacts a septic area or well." Even a small shed or deck addition under that 100-square-foot threshold still has to meet the zoning setbacks for its district, since the same subsection makes clear that "all setbacks must be met for the particular use" regardless of whether a permit is pulled.

Anything larger than 100 square feet, and anything of any size that adds plumbing, a sanitary connection, or affects a septic area or well, needs a full building permit application even if the footprint is small. Because Part 4 Zoning applies only in the zoned areas of unincorporated Allegany County, a property outside a zoned area may not face the same setback trigger, but the underlying Chapter 255 building-permit requirement for structures covered by the adopted IBC and IRC still runs on a county-wide basis. Violating the Building Code, including building without the required permit, carries a fine of $1 to $1,000 under § 255-2.

Violations & Fines

Building without the required permit, or exceeding the 100-square-foot exemption in § 360-62C without applying, violates the Allegany County Building Code under § 255-2. Penalties run $1 to $1,000 per day, with every day of continued unpermitted construction counted as a separate offense, and the property must still meet applicable zoning setbacks even where no permit was required.

Frequently Asked Questions

Do I need a permit for a small shed in unincorporated Allegany County?
Not if it is 100 square feet or smaller and does not involve sanitary facilities or affect a septic area or well, under County Code § 360-62C. The shed still has to meet the setback required for its zoning district, since the exemption only removes the permit step, not the dimensional standards.
What building codes does Allegany County enforce through its permits?
Chapter 255, § 255-1 adopts the 2006 International Building Code and the 2006 International Residential Code, along with the International Mechanical Code, NFPA 70 and NFPA 13D, as the county's 2007 Building Code. A building permit in unincorporated Allegany County confirms the project meets those adopted editions.
What is the penalty for building without a permit?
Section 255-2 makes any violation of the Allegany County Building Code, including unpermitted construction, punishable by a fine of $1 to $1,000, and each day the violation continues is charged as a separate offense until the permit and required inspections are obtained.

Sources & Official References

Other rules in Allegany County

All Allegany County rules

Compare Allegany County to another location·View the Maryland building safety overview

Get notified when Building Permits in Allegany County, MD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.