Key Facts

Adopted electrical code
NFPA 70, National Electric Code (§ 255-1D)
Governing chapter
Chapter 255, Building Construction
Effective date
January 1, 2008, Bill No. 11-07
Penalty
$1 to $1,000 per day of violation
Flood areas
Wiring below flood elevation needs wet-location rating

Summary

Unincorporated Allegany County requires electrical work to meet NFPA 70, the National Electric Code, which § 255-1D of the Building Construction chapter adopts by reference as part of the county's 2007 Building Code. An electrical permit confirms wiring, panels and fixtures meet that adopted national standard before the county signs off.

These county ordinances apply to unincorporated areas of Allegany County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The following codes and any subsequent amendments are hereby adopted by reference as the 2007 Building Code of Allegany County, as if the codes were set forth in full in this section, with the additions, insertions, deletions and changes, if any, shown in the Appendix, attached hereto and made a part hereof ... ... D. The National Fire Protection Association Standard No. 70, The National Electric Code.

Full Breakdown

Chapter 255 of the Code of Allegany County, adopted by the Board of County Commissioners on November 8, 2007 under Bill No. 11-07 and effective January 1, 2008, sets out the 2007 Building Code for the unincorporated county. Section 255-1 lists the codes that make up that Building Code, and Subsection D adopts "The National Fire Protection Association Standard No. 70, The National Electric Code" by reference, alongside the 2006 International Building Code, the 2006 International Residential Code, the International Mechanical Code, the Maryland Accessibility Code under COMAR 05.02.02, and NFPA 13D for residential sprinkler systems.

Because NFPA 70 is folded into the county's Building Code rather than published as a separate local ordinance, an electrician or homeowner doing wiring work in unincorporated Allegany County needs a permit under the same Chapter 255 process described in § 360-59: application, plan review, approval, inspection, and a certificate of occupancy before the circuit is put into service. The county's floodplain rules add a related requirement for wiring in flood hazard areas: under § 325-4D(4), electrical systems, equipment and components must sit at or above the elevation required for the lowest floor, and any wiring installed below that elevation has to meet the electrical part of the building code's rules for wet locations.

A violation of any part of the adopted Building Code, including improper or unpermitted electrical work under NFPA 70, is punishable under § 255-2 by a fine of $1 to $1,000, with each day of the violation counted separately.

Violations & Fines

Any violation of the adopted Building Code, including electrical work that skips the required permit or does not meet NFPA 70, the National Electric Code adopted in § 255-1D, is punishable under § 255-2 by a fine of $1 to $1,000. Each day the noncompliant wiring remains in place or in use counts as a separate offense.

Frequently Asked Questions

Does Allegany County have its own electrical code?
No. Section 255-1D of the Code of Allegany County adopts NFPA 70, the National Electric Code, by reference as part of the county's 2007 Building Code rather than writing a separate local electrical ordinance, so permitted wiring work in unincorporated Allegany County is measured against that national standard.
Do I need a permit for electrical work in unincorporated Allegany County?
Yes. Electrical work falls under the Chapter 255 Building Code that adopts NFPA 70, and the permit process in § 360-59 runs through application, plan review, approval and inspection before a certificate of occupancy is issued, so unpermitted wiring is treated as a Building Code violation.
What happens to electrical work that fails inspection?
Electrical work that does not meet the adopted National Electric Code or is installed without the required permit is a violation of the Building Code under § 255-2, carrying a fine of $1 to $1,000 with each day of noncompliance charged as a separate offense until it is corrected and passes inspection.

Sources & Official References

Other rules in Allegany County

All Allegany County rules

Compare Allegany County to another location·View the Maryland building safety overview

Get notified when Electrical Permits in Allegany County, MD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.