Summary
Unincorporated Floyd County requires a building permit from the Chief Building Official before any structure or interior finish work begins, plus a fire prevention and health code sign-off, and bars issuance on any lot that is not a lot of record.
a.Building permits for all structures or interior finishes are issued after meeting the applicable requirements of the fire prevention and life safety code and the various health and building codes. A permit is also required for the movement of any site-built house, structure or building.b.For any structure served by an on-site sewage disposal system, a permit issued by the Floyd County Health Department shall be required prior to issuance of a Building permit. Said permit may first require approval by the Floyd County Health Department of a plan showing the location of the sewage disposal system and other on-site improvements, in accordance with their regulations.c.Building permits shall only be issued on lots of record, as defined in this Development Code.
Full Breakdown
1 of the Unified Land Development Code (Appendix B), titled BUILDING PERMIT REQUIRED, states that building permits for all structures or interior finishes are issued only after meeting the applicable requirements of the fire prevention and life safety code and the various health and building codes, and that a permit is also required to move any site-built house, structure or building. Properties served by an on-site sewage disposal system must first obtain a Floyd County Health Department permit, which may itself require the Health Department's approval of a plan showing the septic system's location, before the county will issue the building permit.
2 sets out the full procedure: the owner must first obtain any required development permit, zoning verification from the Planning Department, and for single-family or two-family homes, a plat or affidavit showing the dwelling meets setback rules. The Chief Building Official checks the application for completeness, and for multi-family or non-residential buildings has two weeks to note compliance issues; once comments are resolved and the State Fire Marshal signs off, the permit issues. Floyd County Code Section 2-6-3(c) separately exempts small agricultural structures in Agricultural-Residential and Suburban Residential zoning districts from needing a building permit, but only if the structure stores farm products or shelters livestock, is not larger than 4,000 square feet or one story taller than 20 feet, has no more than 125 amps of electrical service, contains no toilet facilities, and the owner first files a sworn zoning compliance form.
Violations & Fines
Building permits are issued only on buildable lots of record, per Section 2.8.2(b)(1), and no permit issues before final plat approval or without access established under the Development Code. Constructing, altering or moving a structure without the required permit is unlawful under Section 2-6-1(d) of the Floyd County Code, punishable under Section 2-1-8, with each day of continued violation a separate offense.
Frequently Asked Questions
Do I need a permit to add interior finishes to my home?
Is a permit required to move a house onto a new lot in Floyd County?
Can I build a farm shed without a permit?
Sources & Official References
Other rules in Floyd County
Compare Floyd County to another location·View the Georgia building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.