Haverhill, MA Building Safety: Building Permits (2026)
Key Facts
- Permit issuer
- Inspector of Buildings only (§ 120-3)
- New construction fee
- $25 + $13/$1,000 value
- Permit term
- 6 months (§ 120-7)
- Minor repair exemption
- owner-occupied, up to $1,000 material
- Unpermitted work
- all fees doubled
- Site plan review fee
- $100 before new construction
Summary
Erecting, altering or repairing a building or structure in the City of Haverhill requires a permit from the Inspector of Buildings under Haverhill City Code § 120-5, issued only in strict conformity with Chapter 120 and state law per § 120-3. New construction costs $25 plus $13 per $1,000 of value, and a permit is valid for six months.
Persons desiring to erect, alter or repair buildings or other structures in the City shall make application for a permit to the Inspector of Buildings which application shall be accompanied by plans and specifications of the work proposed to be done, and no such erection, alteration or repairs shall be undertaken until a permit has been issued therefor in accordance with the provisions of this chapter.
Full Breakdown
Section 120-5 requires anyone who wants to erect, alter or repair a building or other structure in the City of Haverhill to apply to the Inspector of Buildings, submitting plans and specifications with the application; no such work may begin until the permit issues. Section 120-3 restricts who can issue that permit: no officer, board, commission or other person besides the Inspector of Buildings may grant a building permit, and every permit must strictly conform to Chapter 120 and the laws of the Commonwealth. The Inspector may also require, under § 120-6, a plot plan of the lot before approving an application, and under § 120-8 can demand a complete set of approved plans be kept on-site during construction.
A building permit issued under this chapter remains valid for six months unless the Inspector revokes it sooner, per § 120-7. Section 120-9 exempts minor repairs from the permit requirement when the owner does the work on the home where they reside, no labor is charged, material costs stay at $1,000 or less per project, and no structural, dimensional or occupancy change results, though emergency repairs after fire, windstorm or catastrophe can proceed first and get permitted later. Fees under § 120-11A run from a $25 application plus $13 per $1,000 of value, no maximum, for new residential or commercial construction, plus a $50 new-residential-occupancy fee, to $50 for the first $2,000 plus $14 per $1,000 thereafter for alterations and repairs, a $100 site plan review fee before new construction, and a $25 reinspection fee. All fees double under § 120-11A(8) if work starts before the permit issues or the Inspector grants permission.
Violations & Fines
Starting work before a permit issues doubles every fee owed under § 120-11A(8), whether the project is new construction, an alteration, a foundation, or a sign. The Inspector of Buildings can also order the suspension of any building operation that does not conform to Chapter 120 under § 120-2, and continuing work after a written suspension order, or refusing an ordered repair, is itself a violation of the chapter.
Frequently Asked Questions
Who issues building permits in Haverhill?
How much does a Haverhill building permit cost?
Do I need a permit for minor home repairs?
How long does a Haverhill building permit last?
Sources & Official References
Other rules in Haverhill
Compare Haverhill to another location·View the Massachusetts building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.