Haverhill, MA Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
National Electrical Code, § 141-1
Permit issued by
Inspector of Wires, § 141-18
Minimum electrical permit fee
$20
100-amp service change fee
$40, incl. 1 meter
200-amp service change fee
$60, incl. 1 meter
Fee schedule location
City Code § 120-11.B

Summary

Haverhill adopts the National Electrical Code by ordinance under City Code § 141-1 and requires a written permit from the Inspector of Wires before any new wiring or alteration work under § 141-18, with fees set in Chapter 120.

§ 141-1. Adopted of standards; enforcement. The National Electric Code of rules and regulations of the National Board of Fire Underwriters for electrical wiring and apparatus as recommended by the National Fire Protection Association is hereby adopted, and it shall be the duty of the Inspector of Wires and of his lawfully authorized deputies to enforce the rules and regulations therein set forth ... § 141-18. Notice and permit required. No person shall within or upon any building or premises, whether private or public, commence any new electrical work or substantially alter or extend any old work until written notice thereof shall have been given to and a written permit therefor issued by the Inspector of Wires. § 141-19. Fees. ... The fees for the permits required by the preceding section shall be as provided in Chapter 120, Building Construction. ... § 120-11. Fees. ... B. Electrical fees. (1) Electrical fees shall be as follows: ... Minimum electrical permit $20 ... 100-amp service change, includes 1 meter $40 200-amp service change, includes 1 meter $60.

Full Breakdown

City Code § 141-1 adopts the National Electric Code of the National Board of Fire Underwriters, as recommended by the National Fire Protection Association, for all electrical wiring and apparatus in the City, and puts the Inspector of Wires and his deputies in charge of enforcing it. Section 141-18 requires written notice to, and a written permit from, the Inspector of Wires before anyone commences new electrical work or substantially alters or extends existing work in any building or premises, public or private. Section 141-19 sends the fee schedule to Chapter 120, Building Construction, where § 120-11.B lists per-job electrical fees: a minimum electrical permit is $20, a 100-amp service change including one meter is $40, a 200-amp service change including one meter is $60, additional meters are $15 each, and appliance work for remodels or alterations runs $20 each.

Section 141-20 lets the Inspector of Wires refuse approval of work that does not conform to the National Electrical Code and lets him impose further reasonable safety requirements. Section 141-23 requires a final inspection and a certificate of satisfactory inspection before current can be turned on, and § 141-21 gives the Inspector a right of entry to buildings under construction to confirm compliance as work progresses.

Violations & Fines

Section 141-3 lets the Inspector order the owner or operator of unsafe wiring to make it safe, and § 141-22 lets the Inspector order unsafe or noncompliant wiring disconnected, with service withheld until he grants written permission to resume. No current may be turned on under § 141-23 until the Inspector issues a certificate of satisfactory inspection. Section 141-6 makes hindering or obstructing the Inspector of Wires a separate offense under the chapter.

Frequently Asked Questions

Do I need a permit for electrical work in Haverhill?
Yes. Section 141-18 requires written notice to the Inspector of Wires and a written permit before starting any new electrical work or substantially altering or extending existing wiring in a building, whether public or private.
What electrical code does Haverhill enforce?
Section 141-1 adopts the National Electric Code of the National Board of Fire Underwriters, as recommended by the National Fire Protection Association, and puts the Inspector of Wires in charge of enforcing it citywide.
How much does an electrical permit cost in Haverhill?
Section 120-11.B sets a $20 minimum electrical permit fee, $40 for a 100-amp service change with one meter, $60 for a 200-amp service change with one meter, and $15 for each additional meter, among other listed items.

Sources & Official References

Other rules in Haverhill

All Haverhill rules

Compare Haverhill to another location·View the Massachusetts building safety overview

Get notified when Electrical Permits in Haverhill, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.