Kendall County, IL Building Safety: Building Permits (2026)
Key Facts
- Adopted codes
- 2024 IBC and IRC, County Code § 8-19
- Permit exemptions
- IRC § R105.2 deleted entirely
- New single-family home fee
- $3,000.00
- Fine range
- $50.00 to $1,000.00 per day
- Permit expiration
- 180 days without work start
- Enforcing agency
- Planning, Building and Zoning
Summary
Unincorporated Kendall County requires a building permit before any covered construction begins, and the County Board deleted the International Residential Code's entire 'Work Exempt From Permit' section, so none of the standard model-code exemptions for small sheds, decks or similar minor work apply here. Planning, Building and Zoning issues permits under the adopted 2024 IBC and IRC and inspects the work through completion.
Sec. 8-25. - International Residential Code. Amendments to the International Residential Code are as follows: ... (2)Sec. R105.2. "Work Exempt From Permit" this section shall be eliminated in its entirety.
Full Breakdown
The County Board adopted the 2024 International Building Code and 2024 International Residential Code, with local amendments, as the Building Code of unincorporated Kendall County (Kendall County Code § 8-19). Section 8-20 makes that Code applicable to every building or structure constructed, enlarged, erected, repaired, altered, demolished, relocated or changed in use within County jurisdiction, so nearly all construction work triggers permitting. Section 8-25 amends the IRC and, in item (2), eliminates Sec. 2, 'Work Exempt From Permit,' in its entirety, meaning small residential projects that other jurisdictions exempt still need a Kendall County permit.
The companion IBC amendment at Section 8-24(5) strikes the parallel building-side exemption. A zoning certificate must be approved and paid for before Planning, Building and Zoning will issue the building permit itself (Kendall County Code § 8-47). 00 per inspection depending on whether the IRC or IBC applies. All permit fees are due before construction begins (Kendall County Code § 8-49). Every permit lapses if work is not started within 180 days of issuance or is suspended for 180 days, though the Planning, Building and Zoning Committee can grant a written extension on permits open more than two years (Kendall County Code § 8-25(3)).
Violations & Fines
Building without the required permit, or working in violation of an approved plan, permit or Code Official directive, is an ordinance violation carrying a fine of $50.00 to $1,000.00, with each day the violation continues after notice treated as a separate offense (Kendall County Code § 8-22). Continuing work after a stop-work order draws the same $50.00 to $1,000.00 fine, and the State's Attorney can pursue other lawful remedies to stop or correct the work.
Frequently Asked Questions
Are small projects like sheds exempt from a Kendall County building permit?
How much does a new home building permit cost in unincorporated Kendall County?
What happens if I build without a permit in Kendall County?
Sources & Official References
Other rules in Kendall County
Compare Kendall County to another location·View the Illinois building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.