Kendall County, IL Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Advance notice required
48 hours before each inspection
Number of stages
12 sequential inspections, §§ 8-34-8-45
Backfill survey
As-built survey required before framing
Final inspection requires
Well/septic/site development approvals
Violation fine
$50.00-$1,000.00 per day, § 8-22

Summary

New construction in unincorporated Kendall County goes through a fixed sequence of inspections from site staking to final occupancy. Kendall County Code § 8-33 requires the owner or contractor to request each inspection 48 hours in advance and keep approved plans on site, and § 8-45 blocks the final occupancy inspection until heating, plumbing, exterior finish, and well and septic approvals are complete.

These county ordinances apply to unincorporated areas of Kendall County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Sec. 8-33. - Inspections. The inspections listed in Sections 8-34 through 8-45 are generally required. The owner or contractor shall request the designated inspection forty-eight (48) hours in advance of the time when such inspection is to be made. An approved set of building plans shall be on the job site for all inspections. Plans not available on the site will be reason for a failed inspection. ... Sec. 8-45. - Final or occupancy permit inspection. Before calling the building office for a final inspection and occupancy permit, construction must be complete, including heating, lighting, water and sanitary hookups, gutters, down spouts, steps, handrails, porches and all exterior finish. Final approvals of well, septic, and site development permits are also required before the release of the certificate of occupancy.

Full Breakdown

Kendall County Code § 8-33 sets the ground rules for every inspection required under the Building Code: the owner or contractor must request the designated inspection at least 48 hours in advance, keep an approved set of building plans on the job site, and have a representative of the property owner present, or the inspection fails. Sections 8-34 through 8-45 then lay out twelve sequential stages: a site inspection at permit application to confirm zoning, floodplain and stormwater compliance (§ 8-34); footing (§ 8-35) and foundation wall (§ 8-36) inspections before concrete is poured; a backfill inspection at least seven days after concrete is poured, which also requires an as-built survey before framing begins (§ 8-37); an electrical service inspection before the utility energizes the site (§ 8-38); framing and wiring inspection once the structure is framed, roofed and rough-wired but before insulation goes in (§ 8-39); underfloor and rough plumbing inspections (§§ 8-40, 8-41); insulation and slab inspections (§§ 8-42, 8-43); a final plumbing inspection during the occupancy inspection (§ 8-44); and the final or occupancy permit inspection itself under § 8-45, which requires heating, lighting, water and sanitary hookups, gutters, downspouts, steps, handrails, porches and exterior finish to be complete, plus final approval of well, septic and site development permits before a certificate of occupancy is released. Missing an inspection or building past a failed stage is treated like any other Building Code violation under Section 8-22.

Violations & Fines

Skipping a required inspection, building past a stage without approval, or continuing work after a failed inspection is enforced as a Building Code violation under Kendall County Code § 8-22, carrying a fine of $50.00 to $1,000.00, with each day of continued violation counted separately. The Code Official can also issue a stop-work order, and ignoring it draws the same fine range.

Frequently Asked Questions

How much notice does Kendall County need before an inspection?
The owner or contractor must request each designated inspection at least 48 hours in advance under Kendall County Code § 8-33, and an approved set of building plans must be on site or the inspection fails.
What has to be done before a final occupancy inspection?
Kendall County Code § 8-45 requires heating, lighting, water and sanitary hookups, gutters, downspouts, steps, handrails, porches and all exterior finish to be complete, plus final approval of well, septic and site development permits, before the certificate of occupancy is released.
Is a survey required during construction?
Yes. Kendall County Code § 8-37 requires an as-built survey, including the top of foundation and distance to lot lines, to be submitted and approved during or after the backfill inspection and before framing begins.

Sources & Official References

Other rules in Kendall County

All Kendall County rules

Compare Kendall County to another location·View the Illinois building safety overview

Get notified when Building Inspections in Kendall County, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.