Lower Merion Township requires a building permit for construction, alteration, demolition and related work under its Uniform Construction Code, Chapter 143. The Code Official in the Department of Building and Planning issues, suspends or revokes permits, and any permit issued in error or on incomplete information can be pulled at any time under Section 403.42 or 403.62 of the UCC as locally amended.

§ 143-4. Permits.

A. Public service agencies. A permit shall not be required for the installation, alteration or repair of generation, transmission, distribution or metering or other related equipment that is under the ownership and control of public service agencies by established right.

B. Suspension or revocation of permit. The Code Official is authorized to suspend or revoke a permit issued under the provisions of this code wherever the permit is issued in error or on the basis of incorrect, inaccurate or incomplete information, or in violation of any ordinance or regulation or any of the provisions of this code.

C. Placement of permit. The building permit, or copy, shall be posted on the site of the work, in a conspicuous location, until the completion of the project.

Full Breakdown

Chapter 143 of the Township Code adopts the Pennsylvania Uniform Construction Code and gives the Director of Building and Planning, as Code Official, authority to enforce it (except the International Fire Code, enforced by the Fire Marshal). Under § 143-4, no permit is required for work by public service agencies on equipment they own and control by established right, but the Code Official can suspend or revoke any permit issued in error, on inaccurate information, or in violation of the code. Once issued, the building permit or a copy must be posted in a conspicuous location on the jobsite until the project is complete.

A permit to demolish a structure will not be issued until the applicant furnishes the Code Official a certificate from a rodent exterminator confirming the structure is free of rodents or has been treated for their eradication. Fees are set under Chapter A167 and must be paid before a permit is valid; § 143-6 lets the Code Official add a penalty fee, on top of the normal permit fee, for anyone who starts work before obtaining the required permit. Local amendments to UCC § 403.43(g) and § 403.63(g) cap a permit's validity at no more than three years from its issue date.

Under § 143-9, working without a required permit, or in conflict with an approved plan or a Code Official directive, is unlawful and exposes the responsible person to fines up to $1,000 per day of continued violation, enforced before a district justice, plus separate authority for the Township to abate or restrain illegal construction.

Violations & Fines

Violating any provision of Chapter 143, including working without the required permit, carries a fine of up to $1,000 per offense, and each day the violation continues counts as a separate offense under § 143-9B. The Code Official can also suspend or revoke a permit issued in error and pursue abatement, stop-work enforcement, or restoration orders independent of any fine.

Frequently Asked Questions

Who issues building permits in Lower Merion Township?
The Code Official, who is the Director of the Township's Department of Building and Planning, issues permits under Chapter 143 of the Township Code, except that fire-related permits fall under the Fire Marshal as Code Official for the International Fire Code portion.
How long is a Lower Merion building permit valid?
Under the local amendment to UCC § 403.43(g)/§ 403.63(g), a permit may be valid for no more than three years from its issue date, after which the work must be completed or a new permit obtained before continuing.
What happens if I start construction before getting a permit?
Section 143-6C authorizes the Code Official to charge an additional fee, on top of the standard permit fee, to anyone who commences work before obtaining the necessary permits, and the work itself risks a stop-work order and fines under § 143-9.

Sources & Official References

Other rules in Lower Merion

All Lower Merion rules

Compare Lower Merion to another location·View the Pennsylvania building safety overview

Get notified when Building Permits in Lower Merion, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Montgomery County handle building permits.

Pottstown, PA
Some Restrictions