Monroe Township (Gloucester County), NJ Building Safety: Building Permits (2026)
Key Facts
- Decision deadline
- 20 business days after application
- Permit expires
- No work in one year, or work stopped six months
- Notice before starting
- At least 24 hours to the Construction Code Official
- Minimum permit fee
- $75 for a basic construction permit
- Plan review fee
- Not less than 20% nor more than 25% of permit fee
- Appeals
- Gloucester County Construction Board of Appeals
- Maximum penalty
- $1,000, 90 days in jail, or both
Summary
In Monroe Township, Gloucester County, construction or alteration of a building or structure cannot start until the Monroe Township Construction Code Enforcing Agency issues a construction permit. The agency must grant or deny an application within 20 business days, and a permit expires if no work starts within one year or work stops for six months.
Every application for a construction permit shall be granted, in whole or in part, or denied within 20 business days. If the application is denied in whole or in part, the Monroe Township Construction Code Enforcing Agency shall set forth the reasons therefor in writing. ... Except as otherwise provided in this article, the construction or alteration of a building or structure shall not be commenced until a construction permit has been issued. The construction of a building or structure shall be in compliance with the approved application for a construction permit and all conditions of site plan approval, if required. ... A construction permit issued in accordance with Subsection A, pursuant to which no construction has been undertaken within one year from the time of issuance, or if construction ceases for a period of six months, the permit shall expire.
Full Breakdown
Article II of Chapter 104 of the Monroe Township Code is the Township's local enabling ordinance for the State Uniform Construction Code. Section 104-17 A creates the 'Monroe Township Construction Code Enforcing Agency,' headed by the Construction Code Official and staffed by Building, Electrical, Fire Protection, Plumbing and Elevator Subcode Officials. Under § 104-17 D, a central permit office receives applications for construction permits and plan review, issues construction permits and certificates of occupancy, collects fees, penalties and fines, and issues notices and orders.
The operative rule is § 104-21 A: except as otherwise provided in the article, construction or alteration of a building or structure shall not be commenced until a construction permit has been issued, and the work must follow the approved application and any site plan approval conditions. Every application must be granted in whole or in part, or denied, within 20 business days. A denial must state its reasons in writing. If the agency lets the period run out, that failure is treated as a denial for purposes of an appeal to the Gloucester County Construction Board of Appeals, unless the applicant agreed to an extension. The agency can approve plan changes that do not require site plan approval.
Two timing rules follow. Section 104-17 E requires at least 24 hours' notice to the Construction Code Official before work starts under a permit. Section 104-21 B expires a permit when no construction has begun within one year of issuance or when construction stops for six months.
Money matters are set in § 104-18. Plan review fees are not less than 20% nor more than 25% of the construction permit charge, are paid at application, are deducted from the permit fee when it is issued, and are not refundable. The minimum fee for a basic construction permit is $75. New construction is charged at $0.038 per cubic foot of volume, and renovations at $34 per $1,000 of estimated cost.
A construction permit is separate from the zoning permit. Section 175-3 A requires the Zoning Officer to issue a zoning permit for the erection, construction, reconstruction, alteration, conversion or installation of a structure or building, and exterior work extending outside the principal structure needs a sealed land survey with the application. Any improvement of 500 square feet or more also goes to Township Engineer review.
Violations & Fines
Under § 104-25 A, violating the article, building in violation of a permit condition, ignoring an order of the Enforcing Agency, or making a false or misleading statement in an application is punishable by a fine of not more than $1,000, imprisonment not exceeding 90 days, or both. Each violation of a permit condition is a separate offense, and penalties are collected in a summary proceeding under the Penalty Enforcement Law. The agency can also suspend, revoke or cancel a permit for neglect, noncompliance or a false statement in the application.
Frequently Asked Questions
Do I need a permit before building or altering something in Monroe Township?
How long does the Township have to decide on an application?
When does a construction permit expire?
Where is a permit denial appealed?
Sources & Official References
Other rules in Monroe Township (Gloucester County)
Compare Monroe Township (Gloucester County) to another location·View the New Jersey building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.